【单选题】You are working on a project forBright Idea In
C、and working on a project for a large retail bank. You have already prepared the WBS and got it signed off.Because of some new government regulations, you need to add some more activities to the WBS. You have got the change requests approved through theCB、The WBS changes in turn require which of the following
A、Cost changes.B、Scope changes.
C、Schedule revisions.D、Risk response change.
网考网参考答案:C
网考网解析:
[解析] 你在Bright Idea公司做一个大型零售仓库的项目。你已经准备了WBS并获得了签字。因为新的政府法规,你需要增加更多活动到WBS。你已经拿到通过CB批准的变更请求。WBS变更依次即将引发下列哪个变更 A) 成本变更。 B) 范围变更。 C) 进度修订。 D) 风险应对变更。 题干表明已经发生WBS,接下来通常是进度变更。