PMP习题练习

PMP考试易错题(2019/7/12)
1题: The WBS,estimates for each work package,and the network diagram are completed.Which of the following would be the NEXT thing for the project manager to do
A.Sequence the activitie
B.Verify that they have the correct scop
C.Create a preliminary schedule and get the team's approva
D.Complete risk managemen
【单选题】:      

2题: 在经济评价中,一个项日内部收益率的决策规划是( )。
A.IRR>0
B.IRR大于或等于基准收益率
C.IRR<0
D.IBR低于基准收益率
【单选题】:      

3题: How should change management be planned for
A.Changes are generally not predictable,therefore planning for change management cannot be sensibl
B.Planning for change management should be done while the various change control processes are being applie
C.Change management can be planned in a set of management plans or a specific change management pla
D.Changes are a sign of bad planninOne should avoid changes during a project thus eliminating the need to manage the
【单选题】:      

4题: 下列会使企业的速动比率提高的经济业务是( )。
A.销售产成品
B.收回应收账款
C.购买短期债券
D.用固定资产对外进行长期投资
【单选题】:      

5题:下列关于“投资总额”与“项目总投资”的阐述正确的是( )。
  • A.前者包含后者
  • B.后者包含前者
  • C.二者所包含的内容部分相关、相同或相近
  • D.二者含义相同



【单选题】:      

 

您正在结束答题

请确认是否提交试卷?

继续做题 确认提交