根据网考网考试中心的统计分析,以下试题在2019/7/22日PMP考试习题练习中,答错率较高,为:49%
【单选题】Which of the following is not considered a cost of nonconformance to quality
- A) Scrap.
- B) Rework.
- C) Expediting.
- D) Process control.