根据网考网考试中心的统计分析,以下试题在2019/9/16日PMP考试习题练习中,答错率较高,为:51%
【单选题】The major disadvantage of a bar chart is:
A Lack of time-phasing.
B Cannot be related to calendar dates.
C does not show activity interrelationships.
D Cannot be related to manpower planning.
E Cannot be related to cost estimates.
网考网参考答案:C,答错率:51%
网考网试题解析: