【单选题】过去几周里,某个初级开发团队成员一直在独立解决项目缺陷。根据执行流程,敏捷项目经理要求高级开发人员对其工作实施代码检查。高级开发人员发现,虽然基本符合功能需求,但代码不符合最佳技术实践。敏捷项目经理下一步应该怎么做? ()
A. 委派另一个开发团队来重新编写代码。
B. 要求开发经理培训初级开发人员,使之了解使用最佳实践的重要性。
C. 与初级开发人员会谈,沟通必须遵循的最佳实践。
D. 安排高级开发人员更频繁开展代码检查。
For the past few weeks, a junior development-team member has been independently working on resolving defects. In accordance with existing processes, the agile projects manger asks a senior developer to complete a code review of their work. The senior developer discovers that, while functional requirements have generally been met, the code did not meet best technical practices. What should agile project managers do next?
A. Assign another development-team to rewrite the codE.
B. Ask the development manager to train the junior developers on the importance of using best practices.
C. Meet with the junior developers to communicate that best practices that must be followeD.
D. Schedule more frequent code reviews with a senior developer.
A. 委派另一个开发团队来重新编写代码。
B. 要求开发经理培训初级开发人员,使之了解使用最佳实践的重要性。
C. 与初级开发人员会谈,沟通必须遵循的最佳实践。
D. 安排高级开发人员更频繁开展代码检查。
For the past few weeks, a junior development-team member has been independently working on resolving defects. In accordance with existing processes, the agile projects manger asks a senior developer to complete a code review of their work. The senior developer discovers that, while functional requirements have generally been met, the code did not meet best technical practices. What should agile project managers do next?
A. Assign another development-team to rewrite the codE.
B. Ask the development manager to train the junior developers on the importance of using best practices.
C. Meet with the junior developers to communicate that best practices that must be followeD.
D. Schedule more frequent code reviews with a senior developer.
【单选题】一个负责领导某组织首支敏捷团队的教练,预期将会遇到与该团队合作之其他团体的阻力。敏捷教练应该怎么做来避免阻力,并更好地促进与其他团体的沟通?()
A. 审查用户故事,描述产品开发的敏捷原则。
B. 制作一个具有区隔线的看板,来描述组织的所有团队。
C. 召开便当讨论会,分享知识并回答问题。
D. 使用价值流图来描述信息在整个组织的流动。
An agile coach leading on organization’s first agile team anticipates resistance from other groups with whom the team will work. What should the agile coach do to avoid resistance and better facilitate communication with the other groups?
A. Review user stories to describe the agile principles of product development.
B. Create a kanban board with swim lanes depicting all organizational teams.
C. Conduct brown bag sessions to share knowledge and answer questions.
D. Use value stream mapping to depict the flow of information throughout the organization.
A. 审查用户故事,描述产品开发的敏捷原则。
B. 制作一个具有区隔线的看板,来描述组织的所有团队。
C. 召开便当讨论会,分享知识并回答问题。
D. 使用价值流图来描述信息在整个组织的流动。
An agile coach leading on organization’s first agile team anticipates resistance from other groups with whom the team will work. What should the agile coach do to avoid resistance and better facilitate communication with the other groups?
A. Review user stories to describe the agile principles of product development.
B. Create a kanban board with swim lanes depicting all organizational teams.
C. Conduct brown bag sessions to share knowledge and answer questions.
D. Use value stream mapping to depict the flow of information throughout the organization.
【单选题】项目团队希望提供工作方法的敏捷性,一位团队成员建议他们尝试新的回顾会议形式,让团队成员可在回顾会议上建议希望在下次冲刺时保持或改变什么。为什么团队应该尝试这种方法? ()
A. 与他们当前的方法相比,这会更加有趣。
B. 可以减少回顾会议的数量。
C. 开展冲刺的新方法应该会对进展计划产生积极影响。
D. 利用新方法来掌握过程改进情况,对团队有帮助。
A project team wants to be more agile in its approach. A team member suggests they try to a new form of retrospective in which team members suggest what they would like to keep or change during the next sprint. Why should the team try this approach?
A. It may be more interesting than their current approach.
B. The number of retrospectives may decreasE.
C. New ways to conduct sprints should have a positive impact on the schedulE.
D. Never ways to capture process improvements may help the team.
A. 与他们当前的方法相比,这会更加有趣。
B. 可以减少回顾会议的数量。
C. 开展冲刺的新方法应该会对进展计划产生积极影响。
D. 利用新方法来掌握过程改进情况,对团队有帮助。
A project team wants to be more agile in its approach. A team member suggests they try to a new form of retrospective in which team members suggest what they would like to keep or change during the next sprint. Why should the team try this approach?
A. It may be more interesting than their current approach.
B. The number of retrospectives may decreasE.
C. New ways to conduct sprints should have a positive impact on the schedulE.
D. Never ways to capture process improvements may help the team.
【单选题】敏捷团队正在创建一个项目的发布计划。发布计划层应包含哪些信息?()
A. 为完成每个任务或故事而将执行的一系列详细活动。
B. 开发人员的概要任务,指出他们需要工作的用户故事。
C. 需要在特定版本中开发的故事详细视图、估算和验收标准。
D. 对可能开发什么以及在什么时间范围开发的粗略视图和期望。
An agile team is creating a project’s release plan. What information should the release plan include?
A. An adequate detailed activities that will be carried out to complete each task or story.
B. Developers high-level tasks that indicate on which user stories they need to work.
C. A detailed view of estimates and acceptance criteria for stories that are to be developed in a particular releasE.
D. A high-level view and expectation about what is likely be developed and in what time framE.
A. 为完成每个任务或故事而将执行的一系列详细活动。
B. 开发人员的概要任务,指出他们需要工作的用户故事。
C. 需要在特定版本中开发的故事详细视图、估算和验收标准。
D. 对可能开发什么以及在什么时间范围开发的粗略视图和期望。
An agile team is creating a project’s release plan. What information should the release plan include?
A. An adequate detailed activities that will be carried out to complete each task or story.
B. Developers high-level tasks that indicate on which user stories they need to work.
C. A detailed view of estimates and acceptance criteria for stories that are to be developed in a particular releasE.
D. A high-level view and expectation about what is likely be developed and in what time framE.
【单选题】在迭代演示过程中,有个新的相关方提到,所交付特性未能满足他们的期望。若要确保在未完项中识别全部需求,产品负责人应该怎么做?()
A. 与发起人开会,解释已按照验收标准交付全部需求。
B. 要求发起人决定应该包含哪些需求,并向全体相关方更新这项决定的信息。
C. 与项目团队一起将新的需求添加到下次迭代中,并向所有相关方更新该变更的相关信息。
D. 确保在需求收集过程中包含所有相关方,并针对新需求召开一次故事编写研讨会。
During an iteration dome, a new stakeholder mentions that the features delivered fail to meet the expectations. What should the product owner do to ensure that all requirements are identified in the backlog?
A. Meet with the sponsor to explain that all requirements were delivered according to the acceptance criteriA.
B. Ask the sponsor to decide what requirements should be included, and update all stakeholders with the decision.
C. Work with the project team to add the new requirements to the next iteration, and update all stakeholders on the changE.
D. Ensure that all stakeholders are included in the requirements collection process, and conduct a story-writing workshop for the new requirements.
A. 与发起人开会,解释已按照验收标准交付全部需求。
B. 要求发起人决定应该包含哪些需求,并向全体相关方更新这项决定的信息。
C. 与项目团队一起将新的需求添加到下次迭代中,并向所有相关方更新该变更的相关信息。
D. 确保在需求收集过程中包含所有相关方,并针对新需求召开一次故事编写研讨会。
During an iteration dome, a new stakeholder mentions that the features delivered fail to meet the expectations. What should the product owner do to ensure that all requirements are identified in the backlog?
A. Meet with the sponsor to explain that all requirements were delivered according to the acceptance criteriA.
B. Ask the sponsor to decide what requirements should be included, and update all stakeholders with the decision.
C. Work with the project team to add the new requirements to the next iteration, and update all stakeholders on the changE.
D. Ensure that all stakeholders are included in the requirements collection process, and conduct a story-writing workshop for the new requirements.