【单选题】在一次冲刺演示中,相关方对产品增量的反馈多数为积极评价,但对一些特性提出了要求。项目团队接下来应该怎么做?()
A. 修改用户故事,并立即着手执行所要求的特性。
B. 更新未完项,添加新特性的故事,并开始估算。
C. 增加反馈和沟通,缩小理解差距。
D. 修订详细项目计划、项目要求、设计文件与测试计划。
During a sprint demo, feedback on product increments was mostly positive, however a few features were requesteD. What should the project team do next?
A. Revise the user stories, and immediately begin implementing the required features.
B. Update the pending with stories for the features and start estimating them.
C. Increase feedback and communication to reduce gap in understanding.
D. Amend the detailed project plans, project requirements, design documents and test plans.
A. 修改用户故事,并立即着手执行所要求的特性。
B. 更新未完项,添加新特性的故事,并开始估算。
C. 增加反馈和沟通,缩小理解差距。
D. 修订详细项目计划、项目要求、设计文件与测试计划。
During a sprint demo, feedback on product increments was mostly positive, however a few features were requesteD. What should the project team do next?
A. Revise the user stories, and immediately begin implementing the required features.
B. Update the pending with stories for the features and start estimating them.
C. Increase feedback and communication to reduce gap in understanding.
D. Amend the detailed project plans, project requirements, design documents and test plans.
【单选题】在为新产品工作时,敏捷团队应该如何确保与外部干系人保持一致? ()
A. 要求产品负责人提供详细的产品规范文件。
B. 查看项目愿景说明书。
C. 召开项目启动大会分配角色。
D. 与Scrum主管合作,确保遵循敏捷原则。
When working on a new product, what should an agile team do to ensure alignment with external stakeholders?
A. Ask the product owner for a detailed product-specification documents.
B. Review the project vision statement.
C. Hold a kick-off meeting to assign roles.
D. Work with the Scrum Master to ensure that agile principles are followeD.
A. 要求产品负责人提供详细的产品规范文件。
B. 查看项目愿景说明书。
C. 召开项目启动大会分配角色。
D. 与Scrum主管合作,确保遵循敏捷原则。
When working on a new product, what should an agile team do to ensure alignment with external stakeholders?
A. Ask the product owner for a detailed product-specification documents.
B. Review the project vision statement.
C. Hold a kick-off meeting to assign roles.
D. Work with the Scrum Master to ensure that agile principles are followeD.
【单选题】某个项目团队经常未能实现交付目标,团队应该怎么做才能更有效率?()
A. 召开定期评审会,识别改进领域,并通过实施变更进行实验。
B. 从约定的迭代未完项中删除几项内容,使之符合近期交付期历史。
C. 审查经验教训登记册,并在产品未完项中添加团队建设事项。
D. 为团队成员制定得到管理支持的自我发展计划。
A project team regularity fails to meet its delivery goals. What should the team do to be more effective?
A. Hold regular reviews to identify areas of improvement, and experiment by implementing changes.
B. Remove items from the agreed-upon iteration backlog to align with recent delivery history.
C. Review the lessons learned register, and add team development items to the product backlog.
D. Create a self-development program for team members that is supported by management.
A. 召开定期评审会,识别改进领域,并通过实施变更进行实验。
B. 从约定的迭代未完项中删除几项内容,使之符合近期交付期历史。
C. 审查经验教训登记册,并在产品未完项中添加团队建设事项。
D. 为团队成员制定得到管理支持的自我发展计划。
A project team regularity fails to meet its delivery goals. What should the team do to be more effective?
A. Hold regular reviews to identify areas of improvement, and experiment by implementing changes.
B. Remove items from the agreed-upon iteration backlog to align with recent delivery history.
C. Review the lessons learned register, and add team development items to the product backlog.
D. Create a self-development program for team members that is supported by management.
【单选题】项目的产品负责人要求Scrum主管推进估算活动。然后,Scrum主管与团队和产品负责人开会,澄清用户故事。会后,团队收集并提供个人用户故事估算。团队采用的是什么方法? ()
A. 计划扑克
B. 宽带德尔菲法
C. 正式点计数法
D. 经验教训
A project’s product owner asked the Scrum Master to facilitate estimation activities. The Scrum Master then meets with the team and product owner to clarify the user story. Following the meeting, the team assembles and provided individual user story estimates. What technique did the team use?
A. Planning poker
B. Wideband Delphi
C. Formal point counting
D. Lessons learned
A. 计划扑克
B. 宽带德尔菲法
C. 正式点计数法
D. 经验教训
A project’s product owner asked the Scrum Master to facilitate estimation activities. The Scrum Master then meets with the team and product owner to clarify the user story. Following the meeting, the team assembles and provided individual user story estimates. What technique did the team use?
A. Planning poker
B. Wideband Delphi
C. Formal point counting
D. Lessons learned
【单选题】在梳理未完项时,产品负责人在评估质量、范围、成本与进度计划的权衡解决方案时首先应该考虑什么? ()
A. 范围
B. 团队历史
C. 给客户带来的价值
D. 问题解决方案
When grooming the backlog, what should the product owner first consider when evaluating trade-offs among quality, scope, cost, and schedule?
A. Scope
B. Team History Review.
C. Value to the custom.
D. Issue solution.
A. 范围
B. 团队历史
C. 给客户带来的价值
D. 问题解决方案
When grooming the backlog, what should the product owner first consider when evaluating trade-offs among quality, scope, cost, and schedule?
A. Scope
B. Team History Review.
C. Value to the custom.
D. Issue solution.