【单选题】您被指派领导地理位置分散的敏捷团队。为了协助沟通、最好的选择是:()
A. 要求团队成员发送自己的照片、以便了解他们的样子。
B. 选择项目沟通的通用语言。
C. 为大家的会面设立一些初步的面对面会议。
D. 定义相同的工作时间、以便每个人都能更好地沟通
You have been assigned to lead a geographically distributed agile team. To assist with communication, the best option would be to:
A. Ask team members to send photos of themselves so you know what they look likE.
B. Choose a common language for project communications.
C. Set up some initial face-to-face meetings for everyone to meet.
D. Define common working hours so everyone can better communicatE.
A. 要求团队成员发送自己的照片、以便了解他们的样子。
B. 选择项目沟通的通用语言。
C. 为大家的会面设立一些初步的面对面会议。
D. 定义相同的工作时间、以便每个人都能更好地沟通
You have been assigned to lead a geographically distributed agile team. To assist with communication, the best option would be to:
A. Ask team members to send photos of themselves so you know what they look likE.
B. Choose a common language for project communications.
C. Set up some initial face-to-face meetings for everyone to meet.
D. Define common working hours so everyone can better communicatE.
【单选题】敏捷开发团队认识到,在当前冲制中无法完成某个故事是因为其复杂性超出之前的估算,若要维持产品质量,团队应怎么做? ()
A. 重新定义“已完成”(DoD、,以便能将该故事记录为“完成”。
B. 延长此次冲刺,以便完成该故事。
C. 将该故事移入产品未完项,并将其分解成便于管理的大小。
D. 在下一个发布版本中完成该故事。
An agile development team realizes that a story cannot be completed during the current sprint because it is more complex than previously estimateD. What should the team do to maintain product quality?
A. Redefine the definition of done (DoD、 so the story can be noted as completE.
B. Extend the sprint so the story can be completeD.
C. Move the story into the product backlog, and break it into manageable sizes.
D. Complete the story during the next releasE.
A. 重新定义“已完成”(DoD、,以便能将该故事记录为“完成”。
B. 延长此次冲刺,以便完成该故事。
C. 将该故事移入产品未完项,并将其分解成便于管理的大小。
D. 在下一个发布版本中完成该故事。
An agile development team realizes that a story cannot be completed during the current sprint because it is more complex than previously estimateD. What should the team do to maintain product quality?
A. Redefine the definition of done (DoD、 so the story can be noted as completE.
B. Extend the sprint so the story can be completeD.
C. Move the story into the product backlog, and break it into manageable sizes.
D. Complete the story during the next releasE.
【单选题】某开发团队计划在当前冲刺期间完成五个故事。在开发首个故事时,确认花费的时间远远超过了原先的计划。团队决定实施这个故事,似乎并不担心冲刺截止期限。敏捷教练应该怎么做?()
A. 从当前冲刺中取消该故事,如何单独创建另一个冲刺,安排其他团队来负责处理这个故事。
B. 向团队强调遵守截止期限的重要性。
C. 与团队开会讨论这个问题并寻找解决方案。
D. 要求产品负责人缩小冲刺范围。
A development team has five stories planned for completing during the current sprint. While developing the first story, the team spends significantly more times originally planneD. The team in determined to implement the story and appear an unconcerned about the sprint deadlinE. What should the agile coach do?
A. Remove the story from the current sprint and create a separate sprint with another team to address this story.
B. Stress the importance of meeting deadline to the team.
C. Meet with the team to discuss and find a resolution for the issuE.
D. Request a reduction in the sprint’s scope from the product owner.
A. 从当前冲刺中取消该故事,如何单独创建另一个冲刺,安排其他团队来负责处理这个故事。
B. 向团队强调遵守截止期限的重要性。
C. 与团队开会讨论这个问题并寻找解决方案。
D. 要求产品负责人缩小冲刺范围。
A development team has five stories planned for completing during the current sprint. While developing the first story, the team spends significantly more times originally planneD. The team in determined to implement the story and appear an unconcerned about the sprint deadlinE. What should the agile coach do?
A. Remove the story from the current sprint and create a separate sprint with another team to address this story.
B. Stress the importance of meeting deadline to the team.
C. Meet with the team to discuss and find a resolution for the issuE.
D. Request a reduction in the sprint’s scope from the product owner.
【单选题】某次冲刺过后,Scrum 主管向团队成员提出了具体且重要的绩效反馈。项目团队成员下一步应该怎么做? ()
A. 解释Scrum主管该如何改进反馈流程。
B. 向Scrum主管说明自己的理由。
C. 要求Scrum主管安排头脑风暴会议,探讨日后如何采取不同的工作方式。
D. 解释其他团队成员的工作如何影响自身工作质量。
After a sprint, the team master provides a team member with specific, critical performers feedback. What should the team member do next?
A. Explain how the scrum master could improve the feedback process.
B. Justify their rational to the scrum master.
C. Ask the scrum master to schedule a brainstorming session on how to work, differently in the futurE.
D. Explain that the work from other team members affected the quality of their work.
A. 解释Scrum主管该如何改进反馈流程。
B. 向Scrum主管说明自己的理由。
C. 要求Scrum主管安排头脑风暴会议,探讨日后如何采取不同的工作方式。
D. 解释其他团队成员的工作如何影响自身工作质量。
After a sprint, the team master provides a team member with specific, critical performers feedback. What should the team member do next?
A. Explain how the scrum master could improve the feedback process.
B. Justify their rational to the scrum master.
C. Ask the scrum master to schedule a brainstorming session on how to work, differently in the futurE.
D. Explain that the work from other team members affected the quality of their work.
【单选题】在回顾会议上,一名团队成员解释延误是因为误解了其他团队设置服务器所需花费的时间,确保不再发生此类情况,敏捷教练下一步应该怎么做? ()
A. 要求其他团队日后更快的设置服务器。
B. 与其他团队开会,了解设置服务器的流程。
C. 将工作分配给可以最快设置服务器的团队。
D. 编写流程,以便其他团队在设置服务器时遵循。
During the retrospective, a team member explained that a delay was caused by a misunderstanding on how long it would take another team to set up a server. What should the agile coach do next to ensure against a recurrence this type?
A. Ask the other team to more quickly set p serves in the futurE.
B. Meeting with other teams to understand the process of setting up a server.
C. Assign the work to the team that can most quickly set up a server.
D. Write a process for the other team to follow when setting up a server.
A. 要求其他团队日后更快的设置服务器。
B. 与其他团队开会,了解设置服务器的流程。
C. 将工作分配给可以最快设置服务器的团队。
D. 编写流程,以便其他团队在设置服务器时遵循。
During the retrospective, a team member explained that a delay was caused by a misunderstanding on how long it would take another team to set up a server. What should the agile coach do next to ensure against a recurrence this type?
A. Ask the other team to more quickly set p serves in the futurE.
B. Meeting with other teams to understand the process of setting up a server.
C. Assign the work to the team that can most quickly set up a server.
D. Write a process for the other team to follow when setting up a server.