【单选题】一个敏捷团队识别到两个发布层面的风险以及四个迭代层面的问题。若要让相关方清楚了解这些情况,团队应该怎么做?()
A. 在一个可见的看板上记录风险和问题,让全体团队成员和相关方均能看到。
B. 分布载有近期已识别风险和问题的每周状态报告。
C. 在每次迭代中添加正在解决的风险和问题,并通过项目迭代报告渠道,向相关方通报最新情况。
D. 为每个风险分配一个负责人,并在每日站会时监督进展情况。
An agile team identifies two risks at the release level and four issues at the iteration level. What should the team do to provide transparency to the stakeholders?
A. Document the risks and issued on a visible board available to all team members and stakeholders.
B. Distribute a weekly status report with a list of recently identified risks and issues.
C. Add resolving risks and issues into each iteration, and update the stakeholders via the project’s iteration reporting channels.
D. Assign an owner to each risk, and monitor progress during daily standups.
A. 在一个可见的看板上记录风险和问题,让全体团队成员和相关方均能看到。
B. 分布载有近期已识别风险和问题的每周状态报告。
C. 在每次迭代中添加正在解决的风险和问题,并通过项目迭代报告渠道,向相关方通报最新情况。
D. 为每个风险分配一个负责人,并在每日站会时监督进展情况。
An agile team identifies two risks at the release level and four issues at the iteration level. What should the team do to provide transparency to the stakeholders?
A. Document the risks and issued on a visible board available to all team members and stakeholders.
B. Distribute a weekly status report with a list of recently identified risks and issues.
C. Add resolving risks and issues into each iteration, and update the stakeholders via the project’s iteration reporting channels.
D. Assign an owner to each risk, and monitor progress during daily standups.
【单选题】敏捷团队正在创建一个项目的发布计划。发布计划层应包含哪些信息?()
A. 为完成每个任务或故事而将执行的一系列详细活动。
B. 开发人员的概要任务,指出他们需要工作的用户故事。
C. 需要在特定版本中开发的故事详细视图、估算和验收标准。
D. 对可能开发什么以及在什么时间范围开发的粗略视图和期望。
An agile team is creating a project’s release plan. What information should the release plan include?
A. An adequate detailed activities that will be carried out to complete each task or story.
B. Developers high-level tasks that indicate on which user stories they need to work.
C. A detailed view of estimates and acceptance criteria for stories that are to be developed in a particular releasE.
D. A high-level view and expectation about what is likely be developed and in what time framE.
A. 为完成每个任务或故事而将执行的一系列详细活动。
B. 开发人员的概要任务,指出他们需要工作的用户故事。
C. 需要在特定版本中开发的故事详细视图、估算和验收标准。
D. 对可能开发什么以及在什么时间范围开发的粗略视图和期望。
An agile team is creating a project’s release plan. What information should the release plan include?
A. An adequate detailed activities that will be carried out to complete each task or story.
B. Developers high-level tasks that indicate on which user stories they need to work.
C. A detailed view of estimates and acceptance criteria for stories that are to be developed in a particular releasE.
D. A high-level view and expectation about what is likely be developed and in what time framE.
【单选题】在迭代演示过程中,有个新的相关方提到,所交付特性未能满足他们的期望。若要确保在未完项中识别全部需求,产品负责人应该怎么做?()
A. 与发起人开会,解释已按照验收标准交付全部需求。
B. 要求发起人决定应该包含哪些需求,并向全体相关方更新这项决定的信息。
C. 与项目团队一起将新的需求添加到下次迭代中,并向所有相关方更新该变更的相关信息。
D. 确保在需求收集过程中包含所有相关方,并针对新需求召开一次故事编写研讨会。
During an iteration dome, a new stakeholder mentions that the features delivered fail to meet the expectations. What should the product owner do to ensure that all requirements are identified in the backlog?
A. Meet with the sponsor to explain that all requirements were delivered according to the acceptance criteriA.
B. Ask the sponsor to decide what requirements should be included, and update all stakeholders with the decision.
C. Work with the project team to add the new requirements to the next iteration, and update all stakeholders on the changE.
D. Ensure that all stakeholders are included in the requirements collection process, and conduct a story-writing workshop for the new requirements.
A. 与发起人开会,解释已按照验收标准交付全部需求。
B. 要求发起人决定应该包含哪些需求,并向全体相关方更新这项决定的信息。
C. 与项目团队一起将新的需求添加到下次迭代中,并向所有相关方更新该变更的相关信息。
D. 确保在需求收集过程中包含所有相关方,并针对新需求召开一次故事编写研讨会。
During an iteration dome, a new stakeholder mentions that the features delivered fail to meet the expectations. What should the product owner do to ensure that all requirements are identified in the backlog?
A. Meet with the sponsor to explain that all requirements were delivered according to the acceptance criteriA.
B. Ask the sponsor to decide what requirements should be included, and update all stakeholders with the decision.
C. Work with the project team to add the new requirements to the next iteration, and update all stakeholders on the changE.
D. Ensure that all stakeholders are included in the requirements collection process, and conduct a story-writing workshop for the new requirements.
【单选题】某敏捷教练正在帮助产品负责人拟定新产品的愿景说明书,以全部描述产品的功能与特性。该项目教练应该如何向产品负责人描述愿景说明书?()
A. 它向目标顾客界定了产品的关键性能指标。
B. 它令人信服地描述了产品如何满足顾客需求。
C. 它全面阐述了应当开发和测试的技术。
D. 它强调了项目的关键目标、范围、成本与时间线。
An agile coach is helping a product owner develop a vision statement instructions describe all functions and features. How should the coach describe the vision statement to the product owner?
A. It describes the product’s key performances indications to target customers.
B. It provides a computing description of how the product meets customers’ needs.
C. It truly articulations the technology that should be developed and testeD.
D. It highlights this key objectives, scope, cost and timeline of this project.
A. 它向目标顾客界定了产品的关键性能指标。
B. 它令人信服地描述了产品如何满足顾客需求。
C. 它全面阐述了应当开发和测试的技术。
D. 它强调了项目的关键目标、范围、成本与时间线。
An agile coach is helping a product owner develop a vision statement instructions describe all functions and features. How should the coach describe the vision statement to the product owner?
A. It describes the product’s key performances indications to target customers.
B. It provides a computing description of how the product meets customers’ needs.
C. It truly articulations the technology that should be developed and testeD.
D. It highlights this key objectives, scope, cost and timeline of this project.
【单选题】由于发生重大问题,对团队产品引擎的一个核心工具进行了升级。在向上级管理层汇报时,如何说明? ()
A. 展示团队速度中的技术债务。
B. 重新估算当前故事。
C. 创建技术债务待办列表。
D. 广泛发布有关此次升级的相关信息。
Due to a major issue, a key tool central to an engine of a team’s product has been upgradeD. How should the team account for this when reporting to upper management?
A. Show the technical debt in the team’s velocity.
B. Reestimate the current stories.
C. Create a technical debt backlog
D. Send out a mass communication about the upgradE.
A. 展示团队速度中的技术债务。
B. 重新估算当前故事。
C. 创建技术债务待办列表。
D. 广泛发布有关此次升级的相关信息。
Due to a major issue, a key tool central to an engine of a team’s product has been upgradeD. How should the team account for this when reporting to upper management?
A. Show the technical debt in the team’s velocity.
B. Reestimate the current stories.
C. Create a technical debt backlog
D. Send out a mass communication about the upgradE.