【单选题】在考虑对项目的影响时,在干系人名单中敏捷项目经理应给予哪位最高优先级? ()
A. 能够妨碍项目实现目标的干系人
B. 能够延迟项目的干系人
C. 能够妨碍项目按预算交付的干系人
D. 能够像朋友一样工作并帮助准备干系人名单的干系人
When considering impact on the project, to whom should an agile project manager give up on the stakeholder list?
A. The stakeholder who can prevent the project from achieving its goals
B. The stakeholders who can delay the project
C. The stakeholder who can prevent the project from delivering within budget
D. The stakeholder who can work as a friend and help prepare the stakeholders list
A. 能够妨碍项目实现目标的干系人
B. 能够延迟项目的干系人
C. 能够妨碍项目按预算交付的干系人
D. 能够像朋友一样工作并帮助准备干系人名单的干系人
When considering impact on the project, to whom should an agile project manager give up on the stakeholder list?
A. The stakeholder who can prevent the project from achieving its goals
B. The stakeholders who can delay the project
C. The stakeholder who can prevent the project from delivering within budget
D. The stakeholder who can work as a friend and help prepare the stakeholders list
【单选题】Based on the table, if team velocity is 5, how many iterations will be needed to complete all stories?
A. 3
B. 4
C. 5
D. 7
根据表格,如果团队的速度为 5,需要多少次迭代来完成所有故事?()
A. 3
B. 4
C. 5
D. 7
A. 3
B. 4
C. 5
D. 7
根据表格,如果团队的速度为 5,需要多少次迭代来完成所有故事?()
A. 3
B. 4
C. 5
D. 7
【单选题】某次冲刺过后,Scrum 主管向团队成员提出了具体且重要的绩效反馈。项目团队成员下一步应该怎么做? ()
A. 解释Scrum主管该如何改进反馈流程。
B. 向Scrum主管说明自己的理由。
C. 要求Scrum主管安排头脑风暴会议,探讨日后如何采取不同的工作方式。
D. 解释其他团队成员的工作如何影响自身工作质量。
After a sprint, the team master provides a team member with specific, critical performers feedback. What should the team member do next?
A. Explain how the scrum master could improve the feedback process.
B. Justify their rational to the scrum master.
C. Ask the scrum master to schedule a brainstorming session on how to work, differently in the futurE.
D. Explain that the work from other team members affected the quality of their work.
A. 解释Scrum主管该如何改进反馈流程。
B. 向Scrum主管说明自己的理由。
C. 要求Scrum主管安排头脑风暴会议,探讨日后如何采取不同的工作方式。
D. 解释其他团队成员的工作如何影响自身工作质量。
After a sprint, the team master provides a team member with specific, critical performers feedback. What should the team member do next?
A. Explain how the scrum master could improve the feedback process.
B. Justify their rational to the scrum master.
C. Ask the scrum master to schedule a brainstorming session on how to work, differently in the futurE.
D. Explain that the work from other team members affected the quality of their work.
【单选题】项目团队遇到由另一个团队管理的网络问题。这些问题阻碍团队成员按照预测进度尽快推进计划工作。Scrum主管下一步应该怎么做? ()
A. 授权团队自行解决问题。
B. 与团队一起解决问题,并召开每日跟进会议。
C. 承担解决问题的责任,以便团队可以专注于自身工作。
D. 要求产品负责人介入,与团队解决。
A project team encounters issues with the network that is managed by another team. These issues preventing team members from proceeding as quickly as expected with planned work. What should the Scrum master do next?
A. Empower the team to solve problems by themselves.
B. Work with the team to resolve the issue, and conduct daily follow-up meetings.
C. Assume ownership for solving the issue so that the team can focus on its work.
D. Ask the product owner to become involved with the term.
A. 授权团队自行解决问题。
B. 与团队一起解决问题,并召开每日跟进会议。
C. 承担解决问题的责任,以便团队可以专注于自身工作。
D. 要求产品负责人介入,与团队解决。
A project team encounters issues with the network that is managed by another team. These issues preventing team members from proceeding as quickly as expected with planned work. What should the Scrum master do next?
A. Empower the team to solve problems by themselves.
B. Work with the team to resolve the issue, and conduct daily follow-up meetings.
C. Assume ownership for solving the issue so that the team can focus on its work.
D. Ask the product owner to become involved with the term.
【单选题】敏捷团队一直根据自身速度,按照预期开展工作,但是,在演示过程中,有个相关方询问为什么这次迭代中没有完成更多工作。敏捷项目领导应该怎么做?()
A. 策划一次鼓舞士气的团队活动。
B. 开展根本原因分析,识别问题并提高速度。
C. 让相关方与团队集中办公。
D. 向相关方说明,团队根据自身速度,按照预期开展工作。
An agile team has been performing as expected according to its velocity. However, during the demo, a stakeholder asks why more was not completed within the iteration. What should the agile project leader do?
A. Plan a morable-boosting team event.
B. Conduct a root cause analysis to identify the problem and increase velocity.
C. Colocate the stakeholder with the team.
D. Inform the stakeholder that the team performed as expected based upon its velocity.
A. 策划一次鼓舞士气的团队活动。
B. 开展根本原因分析,识别问题并提高速度。
C. 让相关方与团队集中办公。
D. 向相关方说明,团队根据自身速度,按照预期开展工作。
An agile team has been performing as expected according to its velocity. However, during the demo, a stakeholder asks why more was not completed within the iteration. What should the agile project leader do?
A. Plan a morable-boosting team event.
B. Conduct a root cause analysis to identify the problem and increase velocity.
C. Colocate the stakeholder with the team.
D. Inform the stakeholder that the team performed as expected based upon its velocity.