【单选题】敏捷开发团队认识到,在当前冲制中无法完成某个故事是因为其复杂性超出之前的估算,若要维持产品质量,团队应怎么做? ()
A. 重新定义“已完成”(DoD、,以便能将该故事记录为“完成”。
B. 延长此次冲刺,以便完成该故事。
C. 将该故事移入产品未完项,并将其分解成便于管理的大小。
D. 在下一个发布版本中完成该故事。
An agile development team realizes that a story cannot be completed during the current sprint because it is more complex than previously estimateD. What should the team do to maintain product quality?
A. Redefine the definition of done (DoD、 so the story can be noted as completE.
B. Extend the sprint so the story can be completeD.
C. Move the story into the product backlog, and break it into manageable sizes.
D. Complete the story during the next releasE.
A. 重新定义“已完成”(DoD、,以便能将该故事记录为“完成”。
B. 延长此次冲刺,以便完成该故事。
C. 将该故事移入产品未完项,并将其分解成便于管理的大小。
D. 在下一个发布版本中完成该故事。
An agile development team realizes that a story cannot be completed during the current sprint because it is more complex than previously estimateD. What should the team do to maintain product quality?
A. Redefine the definition of done (DoD、 so the story can be noted as completE.
B. Extend the sprint so the story can be completeD.
C. Move the story into the product backlog, and break it into manageable sizes.
D. Complete the story during the next releasE.
【单选题】产品未完项中只剩下少数事项,项目管理办公室(PMO)主管现在要审查产品需求。该主管应该审查哪些项目资源? ()
A. 功能集
B. 最终项目审计
C. 验收测试
D. 业务需求文档(BRD、
There are only a few items remaining in the product backlog. The project management office (PMO) director now wants to review the product’s requirements. What project resource should the director review?
A. Feature sets.
B. Final project audits.
C. Acceptance tests.
D. Business requirement documents (BRD、.
A. 功能集
B. 最终项目审计
C. 验收测试
D. 业务需求文档(BRD、
There are only a few items remaining in the product backlog. The project management office (PMO) director now wants to review the product’s requirements. What project resource should the director review?
A. Feature sets.
B. Final project audits.
C. Acceptance tests.
D. Business requirement documents (BRD、.
【单选题】某次冲刺过后,Scrum 主管向团队成员提出了具体且重要的绩效反馈。项目团队成员下一步应该怎么做? ()
A. 解释Scrum主管该如何改进反馈流程。
B. 向Scrum主管说明自己的理由。
C. 要求Scrum主管安排头脑风暴会议,探讨日后如何采取不同的工作方式。
D. 解释其他团队成员的工作如何影响自身工作质量。
After a sprint, the team master provides a team member with specific, critical performers feedback. What should the team member do next?
A. Explain how the scrum master could improve the feedback process.
B. Justify their rational to the scrum master.
C. Ask the scrum master to schedule a brainstorming session on how to work, differently in the futurE.
D. Explain that the work from other team members affected the quality of their work.
A. 解释Scrum主管该如何改进反馈流程。
B. 向Scrum主管说明自己的理由。
C. 要求Scrum主管安排头脑风暴会议,探讨日后如何采取不同的工作方式。
D. 解释其他团队成员的工作如何影响自身工作质量。
After a sprint, the team master provides a team member with specific, critical performers feedback. What should the team member do next?
A. Explain how the scrum master could improve the feedback process.
B. Justify their rational to the scrum master.
C. Ask the scrum master to schedule a brainstorming session on how to work, differently in the futurE.
D. Explain that the work from other team members affected the quality of their work.
【单选题】产品负责人坚称,实施的用户故事将在即将实现的迭代过程中耗尽团队时间。敏捷团队建议去除琐碎任务,以便维持团队速度。敏捷教练应该怎么做? ()
A. 将该问题升级上报给指导委员会和相关方。
B. 将所需的琐碎任务作为“孤儿”任务包含进冲刺中。
C. 推迟琐碎任务,因为它们不能明显增加产品价值。
D. 将琐碎任务委派给其他团队。
A product owner insists that the implemented user stories will drain the team’s time during the upcoming iterations. The agile teams want to What should an agile coach
A. Escalate the issue to the steering committee and relevant parties.
B. Include the required trivial tasks into the sprint as “orphan” tasks.
C. Postpone trivial tasks as they add no clear product values.
D. Delegate trivial tasks to other teams.
A. 将该问题升级上报给指导委员会和相关方。
B. 将所需的琐碎任务作为“孤儿”任务包含进冲刺中。
C. 推迟琐碎任务,因为它们不能明显增加产品价值。
D. 将琐碎任务委派给其他团队。
A product owner insists that the implemented user stories will drain the team’s time during the upcoming iterations. The agile teams want to What should an agile coach
A. Escalate the issue to the steering committee and relevant parties.
B. Include the required trivial tasks into the sprint as “orphan” tasks.
C. Postpone trivial tasks as they add no clear product values.
D. Delegate trivial tasks to other teams.
【单选题】用户正在验收测试某个新的软件系统。虽然多数业务相关方给与了正面评价,但敏捷项目经理指出IT总监并不高兴。敏捷项目经理下一步应该怎么做?()
A. 查看IT总监在之前项目会议的出席情况。
B. 与IT总监一起审查经批准的项目需求。
C. 请IT总监在用户验收测试过程中提出反馈意见。
D. 与IT总监开会,获得坦率反馈。
The user acceptance testing of a new software system is in progress. While most business stakeholders have expressed positive comments the agile project manage learns that the IT director is unpleaseD. What should the agile project manager do next?
A. Check the IT director’s attendance at priori project meetings.
B. Review the approved requirements for the project with the IT director.
C. Ask the IT director to submit feedback during user acceptance testing.
D. Meeting with the IT director to obtain candid feedback.
A. 查看IT总监在之前项目会议的出席情况。
B. 与IT总监一起审查经批准的项目需求。
C. 请IT总监在用户验收测试过程中提出反馈意见。
D. 与IT总监开会,获得坦率反馈。
The user acceptance testing of a new software system is in progress. While most business stakeholders have expressed positive comments the agile project manage learns that the IT director is unpleaseD. What should the agile project manager do next?
A. Check the IT director’s attendance at priori project meetings.
B. Review the approved requirements for the project with the IT director.
C. Ask the IT director to submit feedback during user acceptance testing.
D. Meeting with the IT director to obtain candid feedback.