【单选题】敏捷开发团队认识到,在当前冲制中无法完成某个故事是因为其复杂性超出之前的估算,若要维持产品质量,团队应怎么做? ()
A. 重新定义“已完成”(DoD、,以便能将该故事记录为“完成”。
B. 延长此次冲刺,以便完成该故事。
C. 将该故事移入产品未完项,并将其分解成便于管理的大小。
D. 在下一个发布版本中完成该故事。
An agile development team realizes that a story cannot be completed during the current sprint because it is more complex than previously estimateD. What should the team do to maintain product quality?
A. Redefine the definition of done (DoD、 so the story can be noted as completE.
B. Extend the sprint so the story can be completeD.
C. Move the story into the product backlog, and break it into manageable sizes.
D. Complete the story during the next releasE.
A. 重新定义“已完成”(DoD、,以便能将该故事记录为“完成”。
B. 延长此次冲刺,以便完成该故事。
C. 将该故事移入产品未完项,并将其分解成便于管理的大小。
D. 在下一个发布版本中完成该故事。
An agile development team realizes that a story cannot be completed during the current sprint because it is more complex than previously estimateD. What should the team do to maintain product quality?
A. Redefine the definition of done (DoD、 so the story can be noted as completE.
B. Extend the sprint so the story can be completeD.
C. Move the story into the product backlog, and break it into manageable sizes.
D. Complete the story during the next releasE.
【单选题】在迭代过程中,一名团队成员做出了一项影响另一位成员工作的决定。这造成了冲突,尽管团队成员做出了努力,但仍无法独自解决。敏捷教练应该怎么做?()
A. 与团队成员沟通,帮助他们逐步减弱冲突。
B. 利用权威来干预和消除冲突。
C. 与整个团队开会,重新确立沟通规划。
D. 要求产品负责人介入。
During an iteration, a team member makes a decision that affects the work of another. This creates conflicts, which despite the efforts, they were unable to resolve on their own. What should an agile coach do?
A. Communicate with team members to help them reduce the conflict.
B. Use their authority to intervene and eliminate the conflict.
C. Meeting with the entire team to reestablish the communication rules.
D. Ask the product owner to become involveD.
A. 与团队成员沟通,帮助他们逐步减弱冲突。
B. 利用权威来干预和消除冲突。
C. 与整个团队开会,重新确立沟通规划。
D. 要求产品负责人介入。
During an iteration, a team member makes a decision that affects the work of another. This creates conflicts, which despite the efforts, they were unable to resolve on their own. What should an agile coach do?
A. Communicate with team members to help them reduce the conflict.
B. Use their authority to intervene and eliminate the conflict.
C. Meeting with the entire team to reestablish the communication rules.
D. Ask the product owner to become involveD.
【单选题】过去几周里,某个初级开发团队成员一直在独立解决项目缺陷。根据执行流程,敏捷项目经理要求高级开发人员对其工作实施代码检查。高级开发人员发现,虽然基本符合功能需求,但代码不符合最佳技术实践。敏捷项目经理下一步应该怎么做? ()
A. 委派另一个开发团队来重新编写代码。
B. 要求开发经理培训初级开发人员,使之了解使用最佳实践的重要性。
C. 与初级开发人员会谈,沟通必须遵循的最佳实践。
D. 安排高级开发人员更频繁开展代码检查。
For the past few weeks, a junior development-team member has been independently working on resolving defects. In accordance with existing processes, the agile projects manger asks a senior developer to complete a code review of their work. The senior developer discovers that, while functional requirements have generally been met, the code did not meet best technical practices. What should agile project managers do next?
A. Assign another development-team to rewrite the codE.
B. Ask the development manager to train the junior developers on the importance of using best practices.
C. Meet with the junior developers to communicate that best practices that must be followeD.
D. Schedule more frequent code reviews with a senior developer.
A. 委派另一个开发团队来重新编写代码。
B. 要求开发经理培训初级开发人员,使之了解使用最佳实践的重要性。
C. 与初级开发人员会谈,沟通必须遵循的最佳实践。
D. 安排高级开发人员更频繁开展代码检查。
For the past few weeks, a junior development-team member has been independently working on resolving defects. In accordance with existing processes, the agile projects manger asks a senior developer to complete a code review of their work. The senior developer discovers that, while functional requirements have generally been met, the code did not meet best technical practices. What should agile project managers do next?
A. Assign another development-team to rewrite the codE.
B. Ask the development manager to train the junior developers on the importance of using best practices.
C. Meet with the junior developers to communicate that best practices that must be followeD.
D. Schedule more frequent code reviews with a senior developer.
【单选题】一家建筑设计事务所在为客户设计新房屋,在查看初始平面计划后,客户增加了大量的对立的反馈意见。团队一起讨论如何带动客户继续推进项目。结果,现在有些团队成员希望实施多次迭代,并在与客户再次开会前与管理层一起审查图纸。团队应该怎么做?()
A. 经常征询客户的反馈意见,以了解客户需求,并根据这些需求给客户需求带来的价值来调整材料。
B. 在与客户再次接洽前,完成所有原先规定的图纸,以保持项目进度计划。
C. 将对应的反馈意见记录为风险,并开展定性和定量分析来识别根本原因。
D. 提出变更请求来解决新的需求,并在继续工作前获得客户确认。
An architectural firm is designing a new house for a customer. After a review of the initial plans the customer provided significant contradictory feedback. The team had a discussion about how to involve the customer moving forwarD. As a result, some members of the team now ward for proceed with a number of iterations and review drawings with management before meeting begin with the customer. What should the team do?
A. Obtain frequent feedback from the customer to learn about their needs, and adjust features based on their value to the customer.
B. Maintain the project schedule by completing all originally specified drawings before reengaging with the customer.
C. Log the contradictory feedback as a risk, and perform qualitative and quantitative analysis to identify the root causE.
D. Issue a change request to address new requirements, and obtain customers confirmation.
A. 经常征询客户的反馈意见,以了解客户需求,并根据这些需求给客户需求带来的价值来调整材料。
B. 在与客户再次接洽前,完成所有原先规定的图纸,以保持项目进度计划。
C. 将对应的反馈意见记录为风险,并开展定性和定量分析来识别根本原因。
D. 提出变更请求来解决新的需求,并在继续工作前获得客户确认。
An architectural firm is designing a new house for a customer. After a review of the initial plans the customer provided significant contradictory feedback. The team had a discussion about how to involve the customer moving forwarD. As a result, some members of the team now ward for proceed with a number of iterations and review drawings with management before meeting begin with the customer. What should the team do?
A. Obtain frequent feedback from the customer to learn about their needs, and adjust features based on their value to the customer.
B. Maintain the project schedule by completing all originally specified drawings before reengaging with the customer.
C. Log the contradictory feedback as a risk, and perform qualitative and quantitative analysis to identify the root causE.
D. Issue a change request to address new requirements, and obtain customers confirmation.
【单选题】在迭代结束时,有个相关方要求提供团队的单元测试代码覆盖率及用户验收测试案例副本,但是,团队尚未完成这次迭代的这些文件。项目领导在下次迭代时应该怎么做?()
A. 在编写单元测试代码覆盖率和用户验收测试案例时,包含每个故事的验收标准。
B. 约定“已完成”(DoD、的定义,并传达给相关方与团队。
C. 调整团队的工作流程,确保记录单位测试代码覆盖率和用户验收测试案例。
D. 在回顾会议上讨论相关方期望,并决定纠正措施。
At the end of an iteration, a stakeholder requests a copy of the team’s unit test code coverage and user acceptance test cases. However, the team did not complete them for this iteration. What should the project leader do for the next iteration?
A. Include the acceptance criteria for each story when writing the unit test code coverage and user acceptance test cases.
B. Agree upon the definition of done (DoD、, and communicate it to all stakeholders and the team.
C. Adapt the team’s process to ensure that unit test code coverage and user acceptance test cases are documenteD.
D. Discuss stakeholder expectations at the retrospective, and decide on corrective actions.
A. 在编写单元测试代码覆盖率和用户验收测试案例时,包含每个故事的验收标准。
B. 约定“已完成”(DoD、的定义,并传达给相关方与团队。
C. 调整团队的工作流程,确保记录单位测试代码覆盖率和用户验收测试案例。
D. 在回顾会议上讨论相关方期望,并决定纠正措施。
At the end of an iteration, a stakeholder requests a copy of the team’s unit test code coverage and user acceptance test cases. However, the team did not complete them for this iteration. What should the project leader do for the next iteration?
A. Include the acceptance criteria for each story when writing the unit test code coverage and user acceptance test cases.
B. Agree upon the definition of done (DoD、, and communicate it to all stakeholders and the team.
C. Adapt the team’s process to ensure that unit test code coverage and user acceptance test cases are documenteD.
D. Discuss stakeholder expectations at the retrospective, and decide on corrective actions.