【单选题】在回顾会议上,一名团队成员解释延误是因为误解了其他团队设置服务器所需花费的时间,确保不再发生此类情况,敏捷教练下一步应该怎么做? ()
A. 要求其他团队日后更快的设置服务器。
B. 与其他团队开会,了解设置服务器的流程。
C. 将工作分配给可以最快设置服务器的团队。
D. 编写流程,以便其他团队在设置服务器时遵循。
During the retrospective, a team member explained that a delay was caused by a misunderstanding on how long it would take another team to set up a server. What should the agile coach do next to ensure against a recurrence this type?
A. Ask the other team to more quickly set p serves in the futurE.
B. Meeting with other teams to understand the process of setting up a server.
C. Assign the work to the team that can most quickly set up a server.
D. Write a process for the other team to follow when setting up a server.
A. 要求其他团队日后更快的设置服务器。
B. 与其他团队开会,了解设置服务器的流程。
C. 将工作分配给可以最快设置服务器的团队。
D. 编写流程,以便其他团队在设置服务器时遵循。
During the retrospective, a team member explained that a delay was caused by a misunderstanding on how long it would take another team to set up a server. What should the agile coach do next to ensure against a recurrence this type?
A. Ask the other team to more quickly set p serves in the futurE.
B. Meeting with other teams to understand the process of setting up a server.
C. Assign the work to the team that can most quickly set up a server.
D. Write a process for the other team to follow when setting up a server.
【单选题】在冲刺过程中,团队的首席质保分析师创建了一次刺探来研究某项目自动化测试工具。这次冲刺已接近尾声,但这次刺探却基本没有进展。
Scrum主管下一步应该怎么做?()
A. 强制规定完成此次刺探的确切截止期限。
B. 与分析师一起确定延误的根本原因,并识别可能阻碍进展的因素。
C. 指示分析师根据有支持的自动测试套件来调整工具选择。
D. 重新将工具选择刺探分配给构架团队。并让分析师负责审查和批准工具选择。
During a sprint, a team’s lead quality assurance analyst created a spike is investigating and a test for automated testing. The sprint is almost finished, but little progress has been made on the spikE. What should the Scrum master do next?
A. Mandate a firm deadline for completing the spikE.
B. Determine the root causes of the delay with the analyst, and identify anything that may be impeding progress.
C. Direct the analyst to align tool selection with supported automated test suites.
D. Reassign the tool selection spike to the architecture team, and have the analyst review and approve the selection.
Scrum主管下一步应该怎么做?()
A. 强制规定完成此次刺探的确切截止期限。
B. 与分析师一起确定延误的根本原因,并识别可能阻碍进展的因素。
C. 指示分析师根据有支持的自动测试套件来调整工具选择。
D. 重新将工具选择刺探分配给构架团队。并让分析师负责审查和批准工具选择。
During a sprint, a team’s lead quality assurance analyst created a spike is investigating and a test for automated testing. The sprint is almost finished, but little progress has been made on the spikE. What should the Scrum master do next?
A. Mandate a firm deadline for completing the spikE.
B. Determine the root causes of the delay with the analyst, and identify anything that may be impeding progress.
C. Direct the analyst to align tool selection with supported automated test suites.
D. Reassign the tool selection spike to the architecture team, and have the analyst review and approve the selection.
【单选题】在项目执行过程中,一名团队注意到必须执行某个遗漏的特性。敏捷项目经理下一步应该怎么做? ()
A. 迅速估算、设计和完成故事实施。
B. 要求产品负责人在产品未完项中添加这故事,以便日后进行优先排序和规划。
C. 在回顾会议上,确定在规划阶段遗漏这个故事的根本原因。
D. 延长迭代截止期限,留出实施遗漏故事的时间。
During sprint execution, a team member notices that a missing feature must be implementeD. What should agile project managers do next?
A. Quickly estimate, design, and complete story implementation.
B. Ask the product owner to add the story to the product backlog for future prioritization and planning.
C. During the retrospective, determine the root cause of why the story was missed during the planning stagE.
D. Extend the iteration deadlines to accommodate the implement of the missing stories.
A. 迅速估算、设计和完成故事实施。
B. 要求产品负责人在产品未完项中添加这故事,以便日后进行优先排序和规划。
C. 在回顾会议上,确定在规划阶段遗漏这个故事的根本原因。
D. 延长迭代截止期限,留出实施遗漏故事的时间。
During sprint execution, a team member notices that a missing feature must be implementeD. What should agile project managers do next?
A. Quickly estimate, design, and complete story implementation.
B. Ask the product owner to add the story to the product backlog for future prioritization and planning.
C. During the retrospective, determine the root cause of why the story was missed during the planning stagE.
D. Extend the iteration deadlines to accommodate the implement of the missing stories.
【单选题】一家公司在大幅改动其自身愿景和战略后,有个极受重视的团队成员开始开会迟到,工作质量低下。敏捷教练应该怎么做?()
A. 安排人员检查该团队成员的工作。
B. 审查该个人在团队中的使命感。
C. 与该团队成员讨论绩效管理计划。
D. 在该个人影响团队绩效之前,将其从团队中开除。
After a company make significant changes to its vision and strategy a valued team member begins arrive late to meetings and submit poor-quality work. What should the agile coach do?
A. Require someone to review the team member’s work.
B. Review the individual’s sense of purpose on the team.
C. Discuss a performance management plan with the team member.
D. Remove the individual before they affect the team’s performancE.
A. 安排人员检查该团队成员的工作。
B. 审查该个人在团队中的使命感。
C. 与该团队成员讨论绩效管理计划。
D. 在该个人影响团队绩效之前,将其从团队中开除。
After a company make significant changes to its vision and strategy a valued team member begins arrive late to meetings and submit poor-quality work. What should the agile coach do?
A. Require someone to review the team member’s work.
B. Review the individual’s sense of purpose on the team.
C. Discuss a performance management plan with the team member.
D. Remove the individual before they affect the team’s performancE.
【单选题】在迭代结束时,有个相关方要求提供团队的单元测试代码覆盖率及用户验收测试案例副本,但是,团队尚未完成这次迭代的这些文件。项目领导在下次迭代时应该怎么做?()
A. 在编写单元测试代码覆盖率和用户验收测试案例时,包含每个故事的验收标准。
B. 约定“已完成”(DoD、的定义,并传达给相关方与团队。
C. 调整团队的工作流程,确保记录单位测试代码覆盖率和用户验收测试案例。
D. 在回顾会议上讨论相关方期望,并决定纠正措施。
At the end of an iteration, a stakeholder requests a copy of the team’s unit test code coverage and user acceptance test cases. However, the team did not complete them for this iteration. What should the project leader do for the next iteration?
A. Include the acceptance criteria for each story when writing the unit test code coverage and user acceptance test cases.
B. Agree upon the definition of done (DoD、, and communicate it to all stakeholders and the team.
C. Adapt the team’s process to ensure that unit test code coverage and user acceptance test cases are documenteD.
D. Discuss stakeholder expectations at the retrospective, and decide on corrective actions.
A. 在编写单元测试代码覆盖率和用户验收测试案例时,包含每个故事的验收标准。
B. 约定“已完成”(DoD、的定义,并传达给相关方与团队。
C. 调整团队的工作流程,确保记录单位测试代码覆盖率和用户验收测试案例。
D. 在回顾会议上讨论相关方期望,并决定纠正措施。
At the end of an iteration, a stakeholder requests a copy of the team’s unit test code coverage and user acceptance test cases. However, the team did not complete them for this iteration. What should the project leader do for the next iteration?
A. Include the acceptance criteria for each story when writing the unit test code coverage and user acceptance test cases.
B. Agree upon the definition of done (DoD、, and communicate it to all stakeholders and the team.
C. Adapt the team’s process to ensure that unit test code coverage and user acceptance test cases are documenteD.
D. Discuss stakeholder expectations at the retrospective, and decide on corrective actions.
【单选题】在什么情况下,Scrum应创建一次刺探?()
A. 团队不具备完成任务所需的知识。
B. 新团队成员获得项目的更新信息。
C. 已招募顾问来补充团队资源。
D. 无法确定故事的确切估算。
A. 团队不具备完成任务所需的知识。
B. 新团队成员获得项目的更新信息。
C. 已招募顾问来补充团队资源。
D. 无法确定故事的确切估算。
【单选题】您被指派领导地理位置分散的敏捷团队。为了协助沟通、最好的选择是:()
A. 要求团队成员发送自己的照片、以便了解他们的样子。
B. 选择项目沟通的通用语言。
C. 为大家的会面设立一些初步的面对面会议。
D. 定义相同的工作时间、以便每个人都能更好地沟通
You have been assigned to lead a geographically distributed agile team. To assist with communication, the best option would be to:
A. Ask team members to send photos of themselves so you know what they look likE.
B. Choose a common language for project communications.
C. Set up some initial face-to-face meetings for everyone to meet.
D. Define common working hours so everyone can better communicatE.
A. 要求团队成员发送自己的照片、以便了解他们的样子。
B. 选择项目沟通的通用语言。
C. 为大家的会面设立一些初步的面对面会议。
D. 定义相同的工作时间、以便每个人都能更好地沟通
You have been assigned to lead a geographically distributed agile team. To assist with communication, the best option would be to:
A. Ask team members to send photos of themselves so you know what they look likE.
B. Choose a common language for project communications.
C. Set up some initial face-to-face meetings for everyone to meet.
D. Define common working hours so everyone can better communicatE.
【单选题】一个高知名度项目的两名关键相关方将在下次产品未完项梳理会议期间出外度假,推迟这次会议就可能会影响总体交付时间。产品负责人下一步应该怎么做? ()
A. 在相关方未参加的情况下照常召开会议,并记录以他们的名义做出的假设。
B. 联系相关方的经理,看看他们的假期能否另行安排。
C. 维持当前的未完项,并重新安排会议时间。
D. 确定未完项中是否有足够的故事让团队继续跟进。
Two key stakeholders for a high-profile project will on vacation when me next meeting to groom the product backlog is helD. Delaying the meeting could impact the cover all delivery timelinE. What should the product owner do next?
A. Hold the meeting without the stakeholders, and document the assumptions that were made on their behalF.
B. Approach the stakeholders’ managers to determine if their vacations can be rescheduleD.
C. Maintain the current backlog, and reschedule the meeting.
D. Determine if there are enough stories ready in the backlog for the team to proceeD.
A. 在相关方未参加的情况下照常召开会议,并记录以他们的名义做出的假设。
B. 联系相关方的经理,看看他们的假期能否另行安排。
C. 维持当前的未完项,并重新安排会议时间。
D. 确定未完项中是否有足够的故事让团队继续跟进。
Two key stakeholders for a high-profile project will on vacation when me next meeting to groom the product backlog is helD. Delaying the meeting could impact the cover all delivery timelinE. What should the product owner do next?
A. Hold the meeting without the stakeholders, and document the assumptions that were made on their behalF.
B. Approach the stakeholders’ managers to determine if their vacations can be rescheduleD.
C. Maintain the current backlog, and reschedule the meeting.
D. Determine if there are enough stories ready in the backlog for the team to proceeD.
【单选题】在某次经验教训会议上,精益敏捷项目团队在新产品运输流程中发现了问题,若要确定这些问题,敏捷项目管理人士应该怎么做? ()
A. 创建价值流程图。
B. 识别新的运输软件。
C. 调整周期时间计算。
D. 开展基于风险的刺探。
During a lessons learned meeting, a lean agile project identifies issues with the process to ship new product. What should the agile practitioner do to determine the issues?
A. Create A value stream map.
B. Identify a new shipping softwarE.
C. Adjust cycle-time calculation.
D. conduct risk-based spikE.
A. 创建价值流程图。
B. 识别新的运输软件。
C. 调整周期时间计算。
D. 开展基于风险的刺探。
During a lessons learned meeting, a lean agile project identifies issues with the process to ship new product. What should the agile practitioner do to determine the issues?
A. Create A value stream map.
B. Identify a new shipping softwarE.
C. Adjust cycle-time calculation.
D. conduct risk-based spikE.
【单选题】集中办公的敏捷团队成员如何在不发电子邮件的情况下分享产品交付计划? ()
A. 在下次冲刺规划会议上向相关方分发项目计划。
B. 在所有相关方都能看到的过程中放置信息扩散器。
C. 在每日站会上分享规划活动。
D. 将信息共享职责分配给产品负责人。
How can colocated agile team members share a product delivery plan without sending emails?
A. Distribute the project plan to stakeholders at the next sprint planning meeting.
B. Place an information radiator in a halfway visible to all stakeholders.
C. Share planning activities at the daily standup meeting.
D. Assign the responsibility of information sharing to the product owner.
A. 在下次冲刺规划会议上向相关方分发项目计划。
B. 在所有相关方都能看到的过程中放置信息扩散器。
C. 在每日站会上分享规划活动。
D. 将信息共享职责分配给产品负责人。
How can colocated agile team members share a product delivery plan without sending emails?
A. Distribute the project plan to stakeholders at the next sprint planning meeting.
B. Place an information radiator in a halfway visible to all stakeholders.
C. Share planning activities at the daily standup meeting.
D. Assign the responsibility of information sharing to the product owner.