【单选题】某开发团队希望在产品评审过程中收到客户更好的反馈意见。团队应该怎么做? ()
A. 要求客户在评审过程中亲自操作产品特性,并记录客户的反应。
B. 将产品特性的详细图片文件电子邮件发送给客户,以便其独立评审。
C. 在评审过程中展示产品特性代码,帮助客户更好的了解代码操作。
D. 要求团队的业务系统分析人员在评审过程中为客户操作产品特性。
A development team wants to receive a better customer feedback during product reviews. What should the team do?
A. Ask the customer to operate the product’s features during the review, and record the customer’s reactions.
B. Email detailed image documentation of the product’s features to the customer for their independent review.
C. Show the product’s feature codes during the review to enable better understanding of coding operation.
D. Ask the team’s business systems analyst to operate the product’s feature for the customer during the review.
A. 要求客户在评审过程中亲自操作产品特性,并记录客户的反应。
B. 将产品特性的详细图片文件电子邮件发送给客户,以便其独立评审。
C. 在评审过程中展示产品特性代码,帮助客户更好的了解代码操作。
D. 要求团队的业务系统分析人员在评审过程中为客户操作产品特性。
A development team wants to receive a better customer feedback during product reviews. What should the team do?
A. Ask the customer to operate the product’s features during the review, and record the customer’s reactions.
B. Email detailed image documentation of the product’s features to the customer for their independent review.
C. Show the product’s feature codes during the review to enable better understanding of coding operation.
D. Ask the team’s business systems analyst to operate the product’s feature for the customer during the review.
【单选题】一支新敏捷团队的成员没有共事经历。除达成共识外,团队应该如何处理估算?()
A. 达成专注于缩短周期时间的项目目标。
B. 确定一个给资源工作增加缓冲的流程。
C. 使用能在短暂、定期间隔内达成里程碑的流程。
D. 以足够的准确度来制定估算。
Members of a new agile team have no experience working with each other.
What should the team do to develop its estimates, besides reaching consensus?
A. Agree on a project goal that is focused on decreasing cycle times.
B. Develop a process that adds buffers to resource effects.
C. Use a process that yields milestone of short regular intervals.
D. Create estimates that are demo with just enough accuracy.
A. 达成专注于缩短周期时间的项目目标。
B. 确定一个给资源工作增加缓冲的流程。
C. 使用能在短暂、定期间隔内达成里程碑的流程。
D. 以足够的准确度来制定估算。
Members of a new agile team have no experience working with each other.
What should the team do to develop its estimates, besides reaching consensus?
A. Agree on a project goal that is focused on decreasing cycle times.
B. Develop a process that adds buffers to resource effects.
C. Use a process that yields milestone of short regular intervals.
D. Create estimates that are demo with just enough accuracy.
【单选题】经过六次迭代,项目团队确定平均速度。有鉴于此,产品负责人认识到,可能无法在预期的时间和预算内完成项目固定范围。为了满足原先的工作范围,团队将不得不提高25%的速度。产品负责人下一步应该怎么做? )
A. 团队通过回顾会议来检查和调整,努力找出额外25%的工作能力。
B. 要求经理拨付额外资金,用于补偿团队对满足这项需求而加班的时间。
C. 与客户开会,确定最小可售特性并调整优先级。
D. 在冲刺迭代未完项中另外增加25%的工作项,并要求团队努力提高速度。
After six iterations, a project team determines its average velocity. Based on the product owner realizes that the project’s original fixed scope may not be completed on time nor within budget. To meet the original scope, the team will have to increase its velocity by 25 percent. What should the product owner do next?
A. Tell the team to use retrospectives to inspect and adapt to find 25 percent additional capacity.
B. Ask the manager for additional funding to compensate the team for working extra hours to meet the demanD.
C. Meet with the customer to determine the minimum marketable features and adjust priorities.
D. Add 25 percent more items to the sprint iteration backlog, and ask the team to commit to the increased velocity.
A. 团队通过回顾会议来检查和调整,努力找出额外25%的工作能力。
B. 要求经理拨付额外资金,用于补偿团队对满足这项需求而加班的时间。
C. 与客户开会,确定最小可售特性并调整优先级。
D. 在冲刺迭代未完项中另外增加25%的工作项,并要求团队努力提高速度。
After six iterations, a project team determines its average velocity. Based on the product owner realizes that the project’s original fixed scope may not be completed on time nor within budget. To meet the original scope, the team will have to increase its velocity by 25 percent. What should the product owner do next?
A. Tell the team to use retrospectives to inspect and adapt to find 25 percent additional capacity.
B. Ask the manager for additional funding to compensate the team for working extra hours to meet the demanD.
C. Meet with the customer to determine the minimum marketable features and adjust priorities.
D. Add 25 percent more items to the sprint iteration backlog, and ask the team to commit to the increased velocity.
【单选题】一家公司在大幅改动其自身愿景和战略后,有个极受重视的团队成员开始开会迟到,工作质量低下。敏捷教练应该怎么做?()
A. 安排人员检查该团队成员的工作。
B. 审查该个人在团队中的使命感。
C. 与该团队成员讨论绩效管理计划。
D. 在该个人影响团队绩效之前,将其从团队中开除。
After a company make significant changes to its vision and strategy a valued team member begins arrive late to meetings and submit poor-quality work. What should the agile coach do?
A. Require someone to review the team member’s work.
B. Review the individual’s sense of purpose on the team.
C. Discuss a performance management plan with the team member.
D. Remove the individual before they affect the team’s performancE.
A. 安排人员检查该团队成员的工作。
B. 审查该个人在团队中的使命感。
C. 与该团队成员讨论绩效管理计划。
D. 在该个人影响团队绩效之前,将其从团队中开除。
After a company make significant changes to its vision and strategy a valued team member begins arrive late to meetings and submit poor-quality work. What should the agile coach do?
A. Require someone to review the team member’s work.
B. Review the individual’s sense of purpose on the team.
C. Discuss a performance management plan with the team member.
D. Remove the individual before they affect the team’s performancE.
【单选题】产品负责人要求开发团队在未完项梳理过程中添加某个事项。若要验证所添加的事项能够产生价值这一假设,产品负责人应该怎么做?()
A. 在冲刺评审过程中,接受功能增量。
B. 冲刺规划过程中,在选择产品未完项前设定冲刺目标。
C. 向市场发布产品增量,根据用户和市场来验证。
D. 检查冲刺燃尽图,在每日Scrum时重新确定未完成项的优先量。
A product owner asks the development team to add an item during backlog grooming. What should the product owner do to validate the assumption that the added item will generate value?
A. Accept an increment of functionality during the sprint review.
B. Set the sprint goal before selecting product backlog items during sprint planning.
C. Release a product increment to the market, and validate it against users and the market.
D. Inspect the sprint bumdown, and reprioritize the backlog at the daily scrum.
A. 在冲刺评审过程中,接受功能增量。
B. 冲刺规划过程中,在选择产品未完项前设定冲刺目标。
C. 向市场发布产品增量,根据用户和市场来验证。
D. 检查冲刺燃尽图,在每日Scrum时重新确定未完成项的优先量。
A product owner asks the development team to add an item during backlog grooming. What should the product owner do to validate the assumption that the added item will generate value?
A. Accept an increment of functionality during the sprint review.
B. Set the sprint goal before selecting product backlog items during sprint planning.
C. Release a product increment to the market, and validate it against users and the market.
D. Inspect the sprint bumdown, and reprioritize the backlog at the daily scrum.