【单选题】敏捷团队希望集体决定项目的可能规模。如果他们使用计划扑克技术完成这项工作,那么团队将会做什么? ()
A. 通过使用故事点估算故事的相对规模
B. 通过将其粗略归类来估算故事
C. 通过将其与过去类似功能进行对比老估算故事点
D. 使用点数来估算故事点
An agile teams want to collectively determine the likely size of a project. What will the team do if they use planned poker technology to do this?
A. Estimate the relative size of the story by using story points
B. Estimate the story by placing them in buckets
C. Estimate story points by comparing them to similar past features.
D. Use the number of dots for votes to estimate story points
A. 通过使用故事点估算故事的相对规模
B. 通过将其粗略归类来估算故事
C. 通过将其与过去类似功能进行对比老估算故事点
D. 使用点数来估算故事点
An agile teams want to collectively determine the likely size of a project. What will the team do if they use planned poker technology to do this?
A. Estimate the relative size of the story by using story points
B. Estimate the story by placing them in buckets
C. Estimate story points by comparing them to similar past features.
D. Use the number of dots for votes to estimate story points
【单选题】在冲刺过程中,团队的首席质保分析师创建了一次刺探来研究某项目自动化测试工具。这次冲刺已接近尾声,但这次刺探却基本没有进展。
Scrum主管下一步应该怎么做?()
A. 强制规定完成此次刺探的确切截止期限。
B. 与分析师一起确定延误的根本原因,并识别可能阻碍进展的因素。
C. 指示分析师根据有支持的自动测试套件来调整工具选择。
D. 重新将工具选择刺探分配给构架团队。并让分析师负责审查和批准工具选择。
During a sprint, a team’s lead quality assurance analyst created a spike is investigating and a test for automated testing. The sprint is almost finished, but little progress has been made on the spikE. What should the Scrum master do next?
A. Mandate a firm deadline for completing the spikE.
B. Determine the root causes of the delay with the analyst, and identify anything that may be impeding progress.
C. Direct the analyst to align tool selection with supported automated test suites.
D. Reassign the tool selection spike to the architecture team, and have the analyst review and approve the selection.
Scrum主管下一步应该怎么做?()
A. 强制规定完成此次刺探的确切截止期限。
B. 与分析师一起确定延误的根本原因,并识别可能阻碍进展的因素。
C. 指示分析师根据有支持的自动测试套件来调整工具选择。
D. 重新将工具选择刺探分配给构架团队。并让分析师负责审查和批准工具选择。
During a sprint, a team’s lead quality assurance analyst created a spike is investigating and a test for automated testing. The sprint is almost finished, but little progress has been made on the spikE. What should the Scrum master do next?
A. Mandate a firm deadline for completing the spikE.
B. Determine the root causes of the delay with the analyst, and identify anything that may be impeding progress.
C. Direct the analyst to align tool selection with supported automated test suites.
D. Reassign the tool selection spike to the architecture team, and have the analyst review and approve the selection.
【单选题】在某个敏捷团队的回顾会议上,他们识别出哪些方面进展顺利,哪些方面进展不顺利以及哪些方面可以帮助团队减少项目风险。若要改进风险状况,团队下一步应该怎么做? ()
A. 记录发现结果,并安排在项目结束后召开一次经验教训会议。
B. 创建一些工作项来开展流程改进,并将其添加进上一次迭代的产品未完项。
C. 记录回顾会议结果,由团队张贴在公共区域,并要求团队主管提交给管理层。
D. 创建某个在下次迭代时需要完成的工作项,以查明所识别的风险,并生成今后迭代时的新工作项或任务。
During an agile team’s retrospective they identified what wen well, what did not go well, and what things can help the team decrease risk to the project. What should the team do next to improve risk profile?
A. Document the findings and schedule a lessons learned meeting to be hold at the end of the project.
B. Create a few work items to address process improvements and add them to the product backlog for the last iteration.
C. Document the retrospective findings for the team to post in a shared area and ask the team lead to present to management.
D. Create a work item to be committed to in the next iteration to probe a ring identified and generate new work items or tasks for future iterations.
A. 记录发现结果,并安排在项目结束后召开一次经验教训会议。
B. 创建一些工作项来开展流程改进,并将其添加进上一次迭代的产品未完项。
C. 记录回顾会议结果,由团队张贴在公共区域,并要求团队主管提交给管理层。
D. 创建某个在下次迭代时需要完成的工作项,以查明所识别的风险,并生成今后迭代时的新工作项或任务。
During an agile team’s retrospective they identified what wen well, what did not go well, and what things can help the team decrease risk to the project. What should the team do next to improve risk profile?
A. Document the findings and schedule a lessons learned meeting to be hold at the end of the project.
B. Create a few work items to address process improvements and add them to the product backlog for the last iteration.
C. Document the retrospective findings for the team to post in a shared area and ask the team lead to present to management.
D. Create a work item to be committed to in the next iteration to probe a ring identified and generate new work items or tasks for future iterations.
【单选题】相关方对敏捷团队按时发布产品的能力表示担忧。团队主管应该如何改善这种情况? ()
A. 使用冲突解决方法,确保营造充分安全的环境,方便团队成员之间的健康沟通。
B. 在交付产品前,取消团队的远程工作政策。
C. 外包困难的未完项,避免额外的迭代工作,并尽量减小团队的非故意责任。
D. 在公共场所创建信息扩散器,展示最新项目信息。
Stakeholders are concerned about the agile team’s ability to release the project
deliver products on timE. What should the team lead do to improve this situation?
A. Use conflict resolution to ensure an adequate safe environment for healthy communication among team members.
B. Eliminate any remote work policies for the team until the product is delivereD.
C. Outsource difficult portions of the backlog, avoid additional iterations, and minimize unintentional team accountability.
D. Create an information radiator that display the latest project information in a common spacE.
A. 使用冲突解决方法,确保营造充分安全的环境,方便团队成员之间的健康沟通。
B. 在交付产品前,取消团队的远程工作政策。
C. 外包困难的未完项,避免额外的迭代工作,并尽量减小团队的非故意责任。
D. 在公共场所创建信息扩散器,展示最新项目信息。
Stakeholders are concerned about the agile team’s ability to release the project
deliver products on timE. What should the team lead do to improve this situation?
A. Use conflict resolution to ensure an adequate safe environment for healthy communication among team members.
B. Eliminate any remote work policies for the team until the product is delivereD.
C. Outsource difficult portions of the backlog, avoid additional iterations, and minimize unintentional team accountability.
D. Create an information radiator that display the latest project information in a common spacE.
【单选题】在回顾会议上,一名团队成员解释延误是因为误解了其他团队设置服务器所需花费的时间,确保不再发生此类情况,敏捷教练下一步应该怎么做? ()
A. 要求其他团队日后更快的设置服务器。
B. 与其他团队开会,了解设置服务器的流程。
C. 将工作分配给可以最快设置服务器的团队。
D. 编写流程,以便其他团队在设置服务器时遵循。
During the retrospective, a team member explained that a delay was caused by a misunderstanding on how long it would take another team to set up a server. What should the agile coach do next to ensure against a recurrence this type?
A. Ask the other team to more quickly set p serves in the futurE.
B. Meeting with other teams to understand the process of setting up a server.
C. Assign the work to the team that can most quickly set up a server.
D. Write a process for the other team to follow when setting up a server.
A. 要求其他团队日后更快的设置服务器。
B. 与其他团队开会,了解设置服务器的流程。
C. 将工作分配给可以最快设置服务器的团队。
D. 编写流程,以便其他团队在设置服务器时遵循。
During the retrospective, a team member explained that a delay was caused by a misunderstanding on how long it would take another team to set up a server. What should the agile coach do next to ensure against a recurrence this type?
A. Ask the other team to more quickly set p serves in the futurE.
B. Meeting with other teams to understand the process of setting up a server.
C. Assign the work to the team that can most quickly set up a server.
D. Write a process for the other team to follow when setting up a server.