【单选题】项目团队制定了在四个月之内交付产品的目标。但是,个别团队有自己的具体目标,会阻碍项目团队实现这个目标。敏捷项目经理下一步应该怎么做? ()
A. 通过团队成员修改个人目标,以确保不会阻碍实现项目目标。
B. 解决这一冲突,帮助项目团队成员专注于优先实现项目目标,并调整个人目标。
C. 变更项目交付日期,这样团队成员仍可实现自身个人目标。
D. 要求团队推退任何必须在工作时间完成的个人目标,并主动帮助团队成员寻找非工作时间的解决办法.
A project team has a goal to deliver a product in four months. However, individual teams have specific objectives that will prevent the team from achieving the goal. What should theagile project manager do?
A. Advise team members to revise their individual objectives to ensure that they do not impede with achieving this goal.
B. Address the conflict to help team members focus on ways to prioritize the project goal, and align their individual objectives.
C. Change the project’s delivery date so that team members can still achieve their individual objectives.
D. Ask the team to delay any individual objectives that must be completed during business hours, and offer to help members find after-hours options.
A. 通过团队成员修改个人目标,以确保不会阻碍实现项目目标。
B. 解决这一冲突,帮助项目团队成员专注于优先实现项目目标,并调整个人目标。
C. 变更项目交付日期,这样团队成员仍可实现自身个人目标。
D. 要求团队推退任何必须在工作时间完成的个人目标,并主动帮助团队成员寻找非工作时间的解决办法.
A project team has a goal to deliver a product in four months. However, individual teams have specific objectives that will prevent the team from achieving the goal. What should theagile project manager do?
A. Advise team members to revise their individual objectives to ensure that they do not impede with achieving this goal.
B. Address the conflict to help team members focus on ways to prioritize the project goal, and align their individual objectives.
C. Change the project’s delivery date so that team members can still achieve their individual objectives.
D. Ask the team to delay any individual objectives that must be completed during business hours, and offer to help members find after-hours options.
【单选题】某开发团队希望在产品评审过程中收到客户更好的反馈意见。团队应该怎么做? ()
A. 要求客户在评审过程中亲自操作产品特性,并记录客户的反应。
B. 将产品特性的详细图片文件电子邮件发送给客户,以便其独立评审。
C. 在评审过程中展示产品特性代码,帮助客户更好的了解代码操作。
D. 要求团队的业务系统分析人员在评审过程中为客户操作产品特性。
A development team wants to receive a better customer feedback during product reviews. What should the team do?
A. Ask the customer to operate the product’s features during the review, and record the customer’s reactions.
B. Email detailed image documentation of the product’s features to the customer for their independent review.
C. Show the product’s feature codes during the review to enable better understanding of coding operation.
D. Ask the team’s business systems analyst to operate the product’s feature for the customer during the review.
A. 要求客户在评审过程中亲自操作产品特性,并记录客户的反应。
B. 将产品特性的详细图片文件电子邮件发送给客户,以便其独立评审。
C. 在评审过程中展示产品特性代码,帮助客户更好的了解代码操作。
D. 要求团队的业务系统分析人员在评审过程中为客户操作产品特性。
A development team wants to receive a better customer feedback during product reviews. What should the team do?
A. Ask the customer to operate the product’s features during the review, and record the customer’s reactions.
B. Email detailed image documentation of the product’s features to the customer for their independent review.
C. Show the product’s feature codes during the review to enable better understanding of coding operation.
D. Ask the team’s business systems analyst to operate the product’s feature for the customer during the review.
【单选题】产品未完项中只剩下少数事项,项目管理办公室(PMO)主管现在要审查产品需求。该主管应该审查哪些项目资源? ()
A. 功能集
B. 最终项目审计
C. 验收测试
D. 业务需求文档(BRD、
There are only a few items remaining in the product backlog. The project management office (PMO) director now wants to review the product’s requirements. What project resource should the director review?
A. Feature sets.
B. Final project audits.
C. Acceptance tests.
D. Business requirement documents (BRD、.
A. 功能集
B. 最终项目审计
C. 验收测试
D. 业务需求文档(BRD、
There are only a few items remaining in the product backlog. The project management office (PMO) director now wants to review the product’s requirements. What project resource should the director review?
A. Feature sets.
B. Final project audits.
C. Acceptance tests.
D. Business requirement documents (BRD、.
【单选题】某个项目迭代存在多个问题,项目团队不确定应该由哪些成员负责,敏捷管理专此人士应该怎么做? ()
A. 督促项目领导将问题指派给适宜的团队成员。
B. 主动帮助团队通过透明度和协作来提高效率。
C. 要求产品负责人指示团队对问题进行优先级排序并予以解决。
D. 针对每个问题创建任务,并分配给适宜的团队成员。
A project iteration has multiple issues, and the project team is unsure which members have the responsibility for them. What should the agile practitioner do?
A. Have the project leader assign the issues to appropriate team members.
B. Offer to help the team to be more effective through transparency and collaboration.
C. Ask the product owner to direct the team on prioritizing and addressing the issues.
D. Create tasks for each of the issues, and assign them to the appreciate team members.
A. 督促项目领导将问题指派给适宜的团队成员。
B. 主动帮助团队通过透明度和协作来提高效率。
C. 要求产品负责人指示团队对问题进行优先级排序并予以解决。
D. 针对每个问题创建任务,并分配给适宜的团队成员。
A project iteration has multiple issues, and the project team is unsure which members have the responsibility for them. What should the agile practitioner do?
A. Have the project leader assign the issues to appropriate team members.
B. Offer to help the team to be more effective through transparency and collaboration.
C. Ask the product owner to direct the team on prioritizing and addressing the issues.
D. Create tasks for each of the issues, and assign them to the appreciate team members.
【单选题】敏捷教练正在与一个团队合作,为通过电话请求产品的客户提供服务。在目标承诺和重新规划会议期间,团队成员表示,由于他们缺乏足够的产品知识,无法解决客户请求。敏捷教练应该怎么做?()
A. 促进团队讨论,识别知识差距,并解决这些差距的最佳方式。
B. 在缺乏知识的领域,为团队成员提供培训。
C. 与这些团队的直线经理开会,讨论他们的培养计划。
D. 要求直线经理分配具备所需技术知识的团队成员。
An agile coach is working with a team that serves clients making product requests by phonE. During a daily commitment and replanning meeting, team members stated that they were unable to resolve a client request because they lacked sufficient product knowledgE. What should an agile coach do?
A. Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.
B. Provide the team members with training to in any lacking areas.
C. Meet with the team managers a line manager to discuss their development plans.
D. Ask the line manager to assign team members with required technical knowledgE.
A. 促进团队讨论,识别知识差距,并解决这些差距的最佳方式。
B. 在缺乏知识的领域,为团队成员提供培训。
C. 与这些团队的直线经理开会,讨论他们的培养计划。
D. 要求直线经理分配具备所需技术知识的团队成员。
An agile coach is working with a team that serves clients making product requests by phonE. During a daily commitment and replanning meeting, team members stated that they were unable to resolve a client request because they lacked sufficient product knowledgE. What should an agile coach do?
A. Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.
B. Provide the team members with training to in any lacking areas.
C. Meet with the team managers a line manager to discuss their development plans.
D. Ask the line manager to assign team members with required technical knowledgE.