【单选题】敏捷团队成员参加站会经常迟到,也未能满足截止期限。项目领导认为可能是因为团队自我管理效率低下。项目领导应该怎么做?
A. 协助团队拟定工作协议,规定预期行为规范。
B. 与团队开会,讨论行为并记录行动项。
C. 以身作则示范适当行为,并承担更多领导职责。
D. 安排团队参加并完成敏捷与时间管理培训。
Agile team members are regularly late for standups and fails to meet deadlinE. The team leader believes this might to due to ineffective team self-management. What should the project leader do?
A. Assist the team in creating a working agreement that specifies desired behavioral norms.
B. Meet with the team to discuss the behavior and document action items.
C. Model the appropriate behavior and assume more of a leadership ratE.
D. Arrange for the team to attend and complete agile and time management training.
A. 协助团队拟定工作协议,规定预期行为规范。
B. 与团队开会,讨论行为并记录行动项。
C. 以身作则示范适当行为,并承担更多领导职责。
D. 安排团队参加并完成敏捷与时间管理培训。
Agile team members are regularly late for standups and fails to meet deadlinE. The team leader believes this might to due to ineffective team self-management. What should the project leader do?
A. Assist the team in creating a working agreement that specifies desired behavioral norms.
B. Meet with the team to discuss the behavior and document action items.
C. Model the appropriate behavior and assume more of a leadership ratE.
D. Arrange for the team to attend and complete agile and time management training.
【单选题】某开发团队希望在产品评审过程中收到客户更好的反馈意见。团队应该怎么做? ()
A. 要求客户在评审过程中亲自操作产品特性,并记录客户的反应。
B. 将产品特性的详细图片文件电子邮件发送给客户,以便其独立评审。
C. 在评审过程中展示产品特性代码,帮助客户更好的了解代码操作。
D. 要求团队的业务系统分析人员在评审过程中为客户操作产品特性。
A development team wants to receive a better customer feedback during product reviews. What should the team do?
A. Ask the customer to operate the product’s features during the review, and record the customer’s reactions.
B. Email detailed image documentation of the product’s features to the customer for their independent review.
C. Show the product’s feature codes during the review to enable better understanding of coding operation.
D. Ask the team’s business systems analyst to operate the product’s feature for the customer during the review.
A. 要求客户在评审过程中亲自操作产品特性,并记录客户的反应。
B. 将产品特性的详细图片文件电子邮件发送给客户,以便其独立评审。
C. 在评审过程中展示产品特性代码,帮助客户更好的了解代码操作。
D. 要求团队的业务系统分析人员在评审过程中为客户操作产品特性。
A development team wants to receive a better customer feedback during product reviews. What should the team do?
A. Ask the customer to operate the product’s features during the review, and record the customer’s reactions.
B. Email detailed image documentation of the product’s features to the customer for their independent review.
C. Show the product’s feature codes during the review to enable better understanding of coding operation.
D. Ask the team’s business systems analyst to operate the product’s feature for the customer during the review.
【单选题】MoSCoW方法的用途是什么? ()
A. 跟踪进度
B. 核实产品
C. 确定故事的优先级
D. 估算故事规模
What is the use of the MoSCoW method?
A. Tracking progress
B. Verify a product
C. Prioritize stories
D. Estimate story size
A. 跟踪进度
B. 核实产品
C. 确定故事的优先级
D. 估算故事规模
What is the use of the MoSCoW method?
A. Tracking progress
B. Verify a product
C. Prioritize stories
D. Estimate story size
【单选题】一个敏捷团队识别到两个发布层面的风险以及四个迭代层面的问题。若要让相关方清楚了解这些情况,团队应该怎么做?()
A. 在一个可见的看板上记录风险和问题,让全体团队成员和相关方均能看到。
B. 分布载有近期已识别风险和问题的每周状态报告。
C. 在每次迭代中添加正在解决的风险和问题,并通过项目迭代报告渠道,向相关方通报最新情况。
D. 为每个风险分配一个负责人,并在每日站会时监督进展情况。
An agile team identifies two risks at the release level and four issues at the iteration level. What should the team do to provide transparency to the stakeholders?
A. Document the risks and issued on a visible board available to all team members and stakeholders.
B. Distribute a weekly status report with a list of recently identified risks and issues.
C. Add resolving risks and issues into each iteration, and update the stakeholders via the project’s iteration reporting channels.
D. Assign an owner to each risk, and monitor progress during daily standups.
A. 在一个可见的看板上记录风险和问题,让全体团队成员和相关方均能看到。
B. 分布载有近期已识别风险和问题的每周状态报告。
C. 在每次迭代中添加正在解决的风险和问题,并通过项目迭代报告渠道,向相关方通报最新情况。
D. 为每个风险分配一个负责人,并在每日站会时监督进展情况。
An agile team identifies two risks at the release level and four issues at the iteration level. What should the team do to provide transparency to the stakeholders?
A. Document the risks and issued on a visible board available to all team members and stakeholders.
B. Distribute a weekly status report with a list of recently identified risks and issues.
C. Add resolving risks and issues into each iteration, and update the stakeholders via the project’s iteration reporting channels.
D. Assign an owner to each risk, and monitor progress during daily standups.
【单选题】在迭代演示过程中,有个新的相关方提到,所交付特性未能满足他们的期望。若要确保在未完项中识别全部需求,产品负责人应该怎么做?()
A. 与发起人开会,解释已按照验收标准交付全部需求。
B. 要求发起人决定应该包含哪些需求,并向全体相关方更新这项决定的信息。
C. 与项目团队一起将新的需求添加到下次迭代中,并向所有相关方更新该变更的相关信息。
D. 确保在需求收集过程中包含所有相关方,并针对新需求召开一次故事编写研讨会。
During an iteration dome, a new stakeholder mentions that the features delivered fail to meet the expectations. What should the product owner do to ensure that all requirements are identified in the backlog?
A. Meet with the sponsor to explain that all requirements were delivered according to the acceptance criteriA.
B. Ask the sponsor to decide what requirements should be included, and update all stakeholders with the decision.
C. Work with the project team to add the new requirements to the next iteration, and update all stakeholders on the changE.
D. Ensure that all stakeholders are included in the requirements collection process, and conduct a story-writing workshop for the new requirements.
A. 与发起人开会,解释已按照验收标准交付全部需求。
B. 要求发起人决定应该包含哪些需求,并向全体相关方更新这项决定的信息。
C. 与项目团队一起将新的需求添加到下次迭代中,并向所有相关方更新该变更的相关信息。
D. 确保在需求收集过程中包含所有相关方,并针对新需求召开一次故事编写研讨会。
During an iteration dome, a new stakeholder mentions that the features delivered fail to meet the expectations. What should the product owner do to ensure that all requirements are identified in the backlog?
A. Meet with the sponsor to explain that all requirements were delivered according to the acceptance criteriA.
B. Ask the sponsor to decide what requirements should be included, and update all stakeholders with the decision.
C. Work with the project team to add the new requirements to the next iteration, and update all stakeholders on the changE.
D. Ensure that all stakeholders are included in the requirements collection process, and conduct a story-writing workshop for the new requirements.