【单选题】产品负责人坚称,实施的用户故事将在即将实现的迭代过程中耗尽团队时间。敏捷团队建议去除琐碎任务,以便维持团队速度。敏捷教练应该怎么做? ()
A. 将该问题升级上报给指导委员会和相关方。
B. 将所需的琐碎任务作为“孤儿”任务包含进冲刺中。
C. 推迟琐碎任务,因为它们不能明显增加产品价值。
D. 将琐碎任务委派给其他团队。
A product owner insists that the implemented user stories will drain the team’s time during the upcoming iterations. The agile teams want to What should an agile coach
A. Escalate the issue to the steering committee and relevant parties.
B. Include the required trivial tasks into the sprint as “orphan” tasks.
C. Postpone trivial tasks as they add no clear product values.
D. Delegate trivial tasks to other teams.
A. 将该问题升级上报给指导委员会和相关方。
B. 将所需的琐碎任务作为“孤儿”任务包含进冲刺中。
C. 推迟琐碎任务,因为它们不能明显增加产品价值。
D. 将琐碎任务委派给其他团队。
A product owner insists that the implemented user stories will drain the team’s time during the upcoming iterations. The agile teams want to What should an agile coach
A. Escalate the issue to the steering committee and relevant parties.
B. Include the required trivial tasks into the sprint as “orphan” tasks.
C. Postpone trivial tasks as they add no clear product values.
D. Delegate trivial tasks to other teams.
【单选题】敏捷教练正在与一个团队合作,为通过电话请求产品的客户提供服务。在目标承诺和重新规划会议期间,团队成员表示,由于他们缺乏足够的产品知识,无法解决客户请求。敏捷教练应该怎么做?()
A. 促进团队讨论,识别知识差距,并解决这些差距的最佳方式。
B. 在缺乏知识的领域,为团队成员提供培训。
C. 与这些团队的直线经理开会,讨论他们的培养计划。
D. 要求直线经理分配具备所需技术知识的团队成员。
An agile coach is working with a team that serves clients making product requests by phonE. During a daily commitment and replanning meeting, team members stated that they were unable to resolve a client request because they lacked sufficient product knowledgE. What should an agile coach do?
A. Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.
B. Provide the team members with training to in any lacking areas.
C. Meet with the team managers a line manager to discuss their development plans.
D. Ask the line manager to assign team members with required technical knowledgE.
A. 促进团队讨论,识别知识差距,并解决这些差距的最佳方式。
B. 在缺乏知识的领域,为团队成员提供培训。
C. 与这些团队的直线经理开会,讨论他们的培养计划。
D. 要求直线经理分配具备所需技术知识的团队成员。
An agile coach is working with a team that serves clients making product requests by phonE. During a daily commitment and replanning meeting, team members stated that they were unable to resolve a client request because they lacked sufficient product knowledgE. What should an agile coach do?
A. Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.
B. Provide the team members with training to in any lacking areas.
C. Meet with the team managers a line manager to discuss their development plans.
D. Ask the line manager to assign team members with required technical knowledgE.
【单选题】产品未完项中只剩下少数事项,项目管理办公室(PMO)主管现在要审查产品需求。该主管应该审查哪些项目资源? ()
A. 功能集
B. 最终项目审计
C. 验收测试
D. 业务需求文档(BRD、
There are only a few items remaining in the product backlog. The project management office (PMO) director now wants to review the product’s requirements. What project resource should the director review?
A. Feature sets.
B. Final project audits.
C. Acceptance tests.
D. Business requirement documents (BRD、.
A. 功能集
B. 最终项目审计
C. 验收测试
D. 业务需求文档(BRD、
There are only a few items remaining in the product backlog. The project management office (PMO) director now wants to review the product’s requirements. What project resource should the director review?
A. Feature sets.
B. Final project audits.
C. Acceptance tests.
D. Business requirement documents (BRD、.
【单选题】一家公司负责人出席开发团队的冲刺评审会议,但不理解敏捷术语。在下次冲刺评审前,项目经理应该怎么做?()
A. 要求开发团队避免使用敏捷术语。
B. 为敏捷单词和词组开发出替代词汇。
C. 为该公司负责人安排一系列敏捷培训会。
D. 调整敏捷流程,使之契合更常用的术语。
A company owner attends the development team’s sprint review meetings, but fails to understand the agile terminology. What should the project manager do prior to the next sprint review?
A. Ask the development team to avoid the use of agile terminology.
B. Develop an alternative vocabulary for agile words and phrases.
C. Schedule a series of agile training meetings with the company owner.
D. Rework agile processes to agile with more established terminology.
A. 要求开发团队避免使用敏捷术语。
B. 为敏捷单词和词组开发出替代词汇。
C. 为该公司负责人安排一系列敏捷培训会。
D. 调整敏捷流程,使之契合更常用的术语。
A company owner attends the development team’s sprint review meetings, but fails to understand the agile terminology. What should the project manager do prior to the next sprint review?
A. Ask the development team to avoid the use of agile terminology.
B. Develop an alternative vocabulary for agile words and phrases.
C. Schedule a series of agile training meetings with the company owner.
D. Rework agile processes to agile with more established terminology.
【单选题】一个高知名度项目的两名关键相关方将在下次产品未完项梳理会议期间出外度假,推迟这次会议就可能会影响总体交付时间。产品负责人下一步应该怎么做? ()
A. 在相关方未参加的情况下照常召开会议,并记录以他们的名义做出的假设。
B. 联系相关方的经理,看看他们的假期能否另行安排。
C. 维持当前的未完项,并重新安排会议时间。
D. 确定未完项中是否有足够的故事让团队继续跟进。
Two key stakeholders for a high-profile project will on vacation when me next meeting to groom the product backlog is helD. Delaying the meeting could impact the cover all delivery timelinE. What should the product owner do next?
A. Hold the meeting without the stakeholders, and document the assumptions that were made on their behalF.
B. Approach the stakeholders’ managers to determine if their vacations can be rescheduleD.
C. Maintain the current backlog, and reschedule the meeting.
D. Determine if there are enough stories ready in the backlog for the team to proceeD.
A. 在相关方未参加的情况下照常召开会议,并记录以他们的名义做出的假设。
B. 联系相关方的经理,看看他们的假期能否另行安排。
C. 维持当前的未完项,并重新安排会议时间。
D. 确定未完项中是否有足够的故事让团队继续跟进。
Two key stakeholders for a high-profile project will on vacation when me next meeting to groom the product backlog is helD. Delaying the meeting could impact the cover all delivery timelinE. What should the product owner do next?
A. Hold the meeting without the stakeholders, and document the assumptions that were made on their behalF.
B. Approach the stakeholders’ managers to determine if their vacations can be rescheduleD.
C. Maintain the current backlog, and reschedule the meeting.
D. Determine if there are enough stories ready in the backlog for the team to proceeD.