【单选题】用户正在验收测试某个新的软件系统。虽然多数业务相关方给与了正面评价,但敏捷项目经理指出IT总监并不高兴。敏捷项目经理下一步应该怎么做?()
A. 查看IT总监在之前项目会议的出席情况。
B. 与IT总监一起审查经批准的项目需求。
C. 请IT总监在用户验收测试过程中提出反馈意见。
D. 与IT总监开会,获得坦率反馈。
The user acceptance testing of a new software system is in progress. While most business stakeholders have expressed positive comments the agile project manage learns that the IT director is unpleaseD. What should the agile project manager do next?
A. Check the IT director’s attendance at priori project meetings.
B. Review the approved requirements for the project with the IT director.
C. Ask the IT director to submit feedback during user acceptance testing.
D. Meeting with the IT director to obtain candid feedback.
A. 查看IT总监在之前项目会议的出席情况。
B. 与IT总监一起审查经批准的项目需求。
C. 请IT总监在用户验收测试过程中提出反馈意见。
D. 与IT总监开会,获得坦率反馈。
The user acceptance testing of a new software system is in progress. While most business stakeholders have expressed positive comments the agile project manage learns that the IT director is unpleaseD. What should the agile project manager do next?
A. Check the IT director’s attendance at priori project meetings.
B. Review the approved requirements for the project with the IT director.
C. Ask the IT director to submit feedback during user acceptance testing.
D. Meeting with the IT director to obtain candid feedback.
【单选题】虽然项目团队一直在完成项目相关方提出的需求,但似乎双方对预期成果不同意见,若要解决团队与相关方的分歧,产品负责人应该怎么做?()
A. 要求相关方与团队一起确定额外需求。
B. 请求相关方更妥善地记录他们所需的要求。
C. 让团队确立“备妥”(DOR)定义:包含相关方的验收标准。
D. 在团队不在场的情况下向相关方演示产品,让其提出反馈意见。
Although a project team has been completing the requirements provided by relevant parties,there seems to be disagreement on the expected outcomE.
What should the product owner do to resolve the disagreement between the team and relevant parties?
A. Have the parties to work with the team to develop additional requirements.
B. Request that relevant parties better document their needed requirements.
C. Have the team establish a definition of ready (DOR) that includes acceptance criteria for the parties concerneD.
D. Demonstrate the product to relevant parties for their feedback without the team in attendancE.
A. 要求相关方与团队一起确定额外需求。
B. 请求相关方更妥善地记录他们所需的要求。
C. 让团队确立“备妥”(DOR)定义:包含相关方的验收标准。
D. 在团队不在场的情况下向相关方演示产品,让其提出反馈意见。
Although a project team has been completing the requirements provided by relevant parties,there seems to be disagreement on the expected outcomE.
What should the product owner do to resolve the disagreement between the team and relevant parties?
A. Have the parties to work with the team to develop additional requirements.
B. Request that relevant parties better document their needed requirements.
C. Have the team establish a definition of ready (DOR) that includes acceptance criteria for the parties concerneD.
D. Demonstrate the product to relevant parties for their feedback without the team in attendancE.
【单选题】敏捷团队在什么阶段使用协作工具 sprint 中显示进度情况?()
A. 概念阶段
B. 规划阶段
C. 评审阶段
D. 执行阶段
At what phase would an agile team use the collaboration tools to show progress during sprints?
A. Inception
B. Planning
C. Review
D. Execution
A. 概念阶段
B. 规划阶段
C. 评审阶段
D. 执行阶段
At what phase would an agile team use the collaboration tools to show progress during sprints?
A. Inception
B. Planning
C. Review
D. Execution
【单选题】某开发团队希望在产品评审过程中收到客户更好的反馈意见。团队应该怎么做? ()
A. 要求客户在评审过程中亲自操作产品特性,并记录客户的反应。
B. 将产品特性的详细图片文件电子邮件发送给客户,以便其独立评审。
C. 在评审过程中展示产品特性代码,帮助客户更好的了解代码操作。
D. 要求团队的业务系统分析人员在评审过程中为客户操作产品特性。
A development team wants to receive a better customer feedback during product reviews. What should the team do?
A. Ask the customer to operate the product’s features during the review, and record the customer’s reactions.
B. Email detailed image documentation of the product’s features to the customer for their independent review.
C. Show the product’s feature codes during the review to enable better understanding of coding operation.
D. Ask the team’s business systems analyst to operate the product’s feature for the customer during the review.
A. 要求客户在评审过程中亲自操作产品特性,并记录客户的反应。
B. 将产品特性的详细图片文件电子邮件发送给客户,以便其独立评审。
C. 在评审过程中展示产品特性代码,帮助客户更好的了解代码操作。
D. 要求团队的业务系统分析人员在评审过程中为客户操作产品特性。
A development team wants to receive a better customer feedback during product reviews. What should the team do?
A. Ask the customer to operate the product’s features during the review, and record the customer’s reactions.
B. Email detailed image documentation of the product’s features to the customer for their independent review.
C. Show the product’s feature codes during the review to enable better understanding of coding operation.
D. Ask the team’s business systems analyst to operate the product’s feature for the customer during the review.
【单选题】一个高知名度项目的两名关键相关方将在下次产品未完项梳理会议期间出外度假,推迟这次会议就可能会影响总体交付时间。产品负责人下一步应该怎么做? ()
A. 在相关方未参加的情况下照常召开会议,并记录以他们的名义做出的假设。
B. 联系相关方的经理,看看他们的假期能否另行安排。
C. 维持当前的未完项,并重新安排会议时间。
D. 确定未完项中是否有足够的故事让团队继续跟进。
Two key stakeholders for a high-profile project will on vacation when me next meeting to groom the product backlog is helD. Delaying the meeting could impact the cover all delivery timelinE. What should the product owner do next?
A. Hold the meeting without the stakeholders, and document the assumptions that were made on their behalF.
B. Approach the stakeholders’ managers to determine if their vacations can be rescheduleD.
C. Maintain the current backlog, and reschedule the meeting.
D. Determine if there are enough stories ready in the backlog for the team to proceeD.
A. 在相关方未参加的情况下照常召开会议,并记录以他们的名义做出的假设。
B. 联系相关方的经理,看看他们的假期能否另行安排。
C. 维持当前的未完项,并重新安排会议时间。
D. 确定未完项中是否有足够的故事让团队继续跟进。
Two key stakeholders for a high-profile project will on vacation when me next meeting to groom the product backlog is helD. Delaying the meeting could impact the cover all delivery timelinE. What should the product owner do next?
A. Hold the meeting without the stakeholders, and document the assumptions that were made on their behalF.
B. Approach the stakeholders’ managers to determine if their vacations can be rescheduleD.
C. Maintain the current backlog, and reschedule the meeting.
D. Determine if there are enough stories ready in the backlog for the team to proceeD.