解析:The inputs of developing project ma

来源:网考网软件水平 所有评论

【单选题】The inputs of developing project management plan do not include (72) .
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
网考网参考答案:B