The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept B Oversimplification (underestimating) of the nature of the work occurs C The project manager is assigned after the project is defined, and the cost and schedule are approved D A clear objective is not provided E All of the above are possible based upon the situation