【单选题】

A work breakdown structure is most useful for: 

A identifying individual tasks for a project 
B scheduling the start of tasks 
C developing a cost estimate 
D determining potential delays 
E A and C 
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...