【单选题】

Which of the following planning considerations is often overlooked? 

A Planning for project termination. 
B Qualified project manager assignment. 
C Insuring top management support. 
D Clearly defined tasks. 
E All of the above.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

81%的考友选择了A选项

4%的考友选择了B选项

9%的考友选择了C选项

6%的考友选择了D选项