【单选题】

The project charter: 

A Expresses upper management commitment to the project. 
B Provides that authority by which the project will be run. 
C Establishes that organizational structure with the project. 
D Specifies overall objectives and timeframe of the project. 
E All of the above.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

0%的考友选择了B选项

0%的考友选择了C选项

0%的考友选择了D选项