【单选题】
The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF).
D Scheduled time (LF - ES).
E Event.
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
69%的考友答对了