【单选题】

As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:

A Insignificant.
B Reduced.
C Unchanged.
D Increased.
E Doubled.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...