【单选题】

a comprehensive definition of scope management would be:

a. managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
b. approval of the scope baseline.http://ks.examda.com
c. approval of the detailed project charter.
d. configuration control.
e. approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...