【单选题】

a task-oriented family tree of activities is a:

a. detailed plan.
b. linear responsibility chart.
c. work breakdown structure.
d. cost account coding system.
e. work package description.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

59%的考友答对了