试题查看

【单选题】

in the pdm, common constraints include:

a. start-to-start
b. finish-to-start
c. finish-to-finish
d. b and c only
e. a, b, and c.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

74%的考友答对了

你可能感兴趣的试题

foragivencharacteristicinaconstructionprprojectcashreservesareoftenusedforadjustselectiveperceptionis_____ofnewconflictitheworkbreakdownstructure(wbs)isanexcellwhenworkinginanenvironmentthatuseslearniwhenworkinginanenvironmentthatuseslearni