【单选题】

giving a part of project work to a contractor is an example of:

a. risk mitigation
b. risk assignment
c. risk delegation
d. risk deflection
e. risk assumption
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

61%的考友答对了