试题查看
首页
>
PMP考试
> 试题查看
【单选题】
giving a part of project work to a contractor is an example of:
a. risk mitigation
b. risk assignment
c. risk delegation
d. risk deflection
e. risk assumption
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
61%
的考友答对了
你可能感兴趣的试题
projectmanagementhasbeenproventobesucces
therearetwomajortypesofreservesusedonpro
todeterminewhatcausesthemajorityofqualit
在考生文件夹下有一个数据库文件“samp3.mdb”,里面已经设计了表对象“tE
expectancytheoryasappliedtoprojectmanage
anadvertiserwhousesamovieorsportsstartoe