试题查看

首页 > PMP考试 > 试题查看
【单选题】

A ContrACtor EstimAtEs thAt A projECt hAs A 0.5 proBABility oF $200,000 proFit AnD 0.3 proBABility oF $50,000 loss. thE ExpECtED monEtAry vAluE
oF this projECt is:
A. 200000
B. 150000
C. 85000
D. 50000
E. nonE oF thE ABovE.

查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

57%的考友答对了

你可能感兴趣的试题

intheprojectenvironment,theindividualultinwhichofthefollowingtypesofcontractsisimiddle(functional)managershavethegreatesacleardefinitionoftheuser'sneedsservesasr&dprojectmanagersinhigh-techcompaniesmothemajordifferencebetweenpertandcpmnetwo