【单选题】
A ContrACtor EstimAtEs thAt A projECt hAs A 0.5 proBABility oF $200,000 proFit AnD 0.3 proBABility oF $50,000 loss. thE ExpECtED monEtAry vAluE
oF this projECt is:
A. 200000
B. 150000
C. 85000
D. 50000
E. nonE oF thE ABovE.