【单选题】

he work breakdown structure (wbs) is the basis for communicating:

a. project scope, cost control, schedule, quality
b. project objectives, dependencies, plan, cost control
c. project scope, schedule, staffing, cost control
d. project scope, quality, schedule, dependencies
e. project budget, schedule, risk factors, work assignments.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...