试题查看
首页
>
PMP考试
> 试题查看
【单选题】
a work breakdown structure:
a. assures all work is identified
b. subdivides the project into manageable segments
c. provides the project sponsor with a time-phase task summary
d. both a and b
e. all of the above.
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
82%
的考友答对了
你可能感兴趣的试题
aprocesscharacteristichasatruemeanof150a
networkschedulesarepreparedduringthe____
scopemanagement:a.entailsmanagingtheproj
themethodsandtechniquesfordeterminingthe
thetraditionalorganizationalformhasthedi
thingsthatdistort,distract,ormuddletheco