试题查看

首页 > PMP考试 > 试题查看
【单选题】

during project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. the baseline

schedule:
a. now becomes the new schedule, including the changes, and the original baseline is disregarded.
b. is still the original baseline but annotated to reflect that a change has taken place.
c. is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
d. is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
e. is the same since baseline schedules cannot change once the development phase is completed.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

56%的考友答对了

你可能感兴趣的试题

networkschedulesarepreparedduringthe____scopemanagement:a.entailsmanagingtheprojthemethodsandtechniquesfordeterminingthethetraditionalorganizationalformhasthedithingsthatdistort,distract,ormuddlethecowhichisnotaconsiderationinamakeorbuydeci