assume that you have a network where an activity on the critical path can be crashed by two weeks. if the activity is actually crashed by two
weeks, then: a. the project's schedule will be reduced by 2 weeks. b. the available slack on the noncritical paths will increase. c. a new critical path may appear after the crash. d. all of the above. e. a and b only. uts and two outputs are allowed using the critical path method.