【单选题】

fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on

the:
a. buyer
b. third party
c. contractor
d. all of the above
e. none of the above
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

61%的考友答对了