试题查看

首页 > PMP考试 > 试题查看
【单选题】

The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project. 

A budget, schedule 
B quality requirements, schedule 
C size, type of industry 
D nature, size 
E project manager, sponsor 
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

76%的考友答对了

你可能感兴趣的试题