【单选题】

The "rolling wave" or "moving window" concept is used most frequently on projects where: 

A The baseline is frozen for the duration of the project and no scope changes are permitted 
B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes 
C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work 
D Networking techniques are not appropriate 
E All of the above 
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

如答案有误或试题有侵权,请联系我们。[提交反馈][在线客服]

根据网考网移动考试中心的统计,该试题:

65%的考友答对了

你可能感兴趣的试题

UsingtheWBSshownintheSpecialwindow,atypiProjecttradeoffsareusuallymadebycomparinThedegreetowhichacompanyacceptsandutilizProjectmanagementprovidesorganizationswiAsummaryWBSisusuallydevelopedintheAConceApprovaltoproceedisnormallymadeattheendo
版权所有网考网(netkao.com)All Rights Reserved

警告:系统检测到您的账号存在安全风险

抱歉,您的账号因涉嫌违反网考网购买须知被冻结。您可在“网考网” 微信公众号中的“官网服务”- "账号解封申请”申请解封。

微信扫描关注网考网