试题查看

首页 > PMP考试 > 试题查看
【单选题】

The use of the project reports:

A are not necessary on small projects
B provides a means whereby various levels of authority can judge project performance
C provides insight into project areas and the effectiveness of the control systems
D All of the above
E B and C
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

69%的考友答对了

你可能感兴趣的试题

WorkauthorizationformsareneededinordertoTypicalcharacteristicsofaworkpackageinclProblemscanoccurinproperlydefiningaprojeGoingfromLevel2toLevel4intheworkbreakdowFeasibilitystudiesoccurinwhichlifecyclepResourceleveling_____.AAllocatesresource