试题查看

首页 > PMP考试 > 试题查看
【单选题】

 Which of the following is indicative of negative float? 

A The late start date is earlier than the early start date. 
B The critical path supports the imposed end date. 
C The early finish date is equal to the late finish date. 
D When leads are employed in the schedule. 
E The project is sinking. 
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

51%的考友答对了

你可能感兴趣的试题

AcompletionofalocalgovernmentstudyresideSourcesfordataonactivitydurationsandresoTheerectionoffoundationformworkbeforethe"Hardlogic"inthepreparationofanetworkrefAsacontroltool,thebarchart(Gantt)methodsYouaremanaginganinternalprojectwhereavic