【单选题】

Typically, change control systems include  

automatic approval of certain types of changes. An  
example of such a change is one that is—
A. Suggested by the project sponsor
B. The result of an emergency
C. Suggested by the customer
D. Made mandatory by a new regulation
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

81%的考友选择了B选项

1%的考友选择了C选项

16%的考友选择了D选项