【单选题】

While implementing your project,a team member brings to your notice a risk that was not mentioned in the risk response plan.In this case,you should______.
A.accept the risk

B.perform additional risk response planning to control the risk
C.inform the project sponsor
D.use project contingency
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

64%的考友选择了B选项

11%的考友选择了C选项

23%的考友选择了D选项