【单选题】

The identification, definition and selection of the project objectives, as well as the best approach to achieving the project objectives, are identified in the ______ process of the project and documented in the project ______ .

A、initiation (authorization), charter
B、initiation (authorization), scope statement
C、scope definition, scope statement
D、scope planning, charter
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

1%的考友选择了A选项

7%的考友选择了B选项

84%的考友选择了C选项

8%的考友选择了D选项