【单选题】

The owner (buyer)of a project usually has the right to direct changes to the scope of work while the project work is being accomplisheD、Often, the owner will orally request a change and insist that the change be initiated immediately without the normal documentation (e. g. a change order). When the change is initiated without documentation, ______ .

A、the owner assumes all responsibility for paying for the change although the owner may at a later not want the change
B、the owner assumes responsibility for one-half the cost of the change until the documentation is completed and all at the same time
C、the project manager assumes all risk for the change, if initiated, until the documentation is received
D、the project manager assumes only the risk of misinterpreting the owner’s oral change directive, while the owner assumes responsibility for paying for the request change
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

22%的考友选择了B选项

76%的考友选择了C选项

2%的考友选择了D选项