试题查看

首页 > PMP考试 > 试题查看
【单选题】

All of the following are examples of a source of scope changeEXCEPT ______ .

A、a variation in government regulations
B、failure to include a required feature in the design of a telecommunication system
C、discovering a need to engage in bottom-up cost estimating
D、introducing technology that was not available when scope was originally defined
查看答案解析

参考答案:

正在加载...