Decomposition is the subdivision of project deliverables into smaller, more manageable components until the work and deliverables are defined at the work package level. This is a valuable tool for define scope. However, decomposition may not be possible for a deliverable or subproject if:

A、The deliverable or subproject is very complicate
B.The deliverable or subproject is already being produce
C.The deliverable or subproject will be accomplished after a very long time ( far into the futu
D.None of the above:Decomposition of deliverables is always possibl