【单选题】

Your project has a number of different work results.You are collecting information about these work results,such as what costs have been incurred or committed and which deliverables have been completed and which remain outstanding.You will use this information in which of the following processes

A、Project plan executio
B.Integrated change contro
C.Report performanc
D.Verify scop
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

5%的考友选择了A选项

21%的考友选择了B选项

73%的考友选择了C选项

1%的考友选择了D选项