【单选题】

You are project manager leading a US $4000000 mechanical engineering project.To date,you’ve been leading the other 11 people who comprise the overall project team.Lately you’ve noticed that you are spread too thin and the schedule is being negatively impacteD、Because the project is date constrained,you convinced senior management to accept a cost variance and add a senior quality assurance analyst to the project team.This new resource will work directly with the three project team members who comprise the testing subteam.How many more communication channels will there be on the project team

A、12.
B.11.
C.78.
D.66.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

73%的考友选择了A选项

21%的考友选择了B选项

5%的考友选择了C选项

1%的考友选择了D选项