【单选题】

In your project,you conducted communications requirements analysis to determine sum of information needs for all stakeholders.You have determined and limited who will communicate with whom and who will receive what information.One factor that you considered while doing communications requirements analysis is that for your project,the number of communication channels______.

A、increases in direct proportion to number of people
B.decreases in inverse proportion to number of people
C.increases in exponential proportion when number of people increases
D.none of the above number of communication channels depends on the type of your project
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

14%的考友选择了A选项

7%的考友选择了B选项

52%的考友选择了C选项

27%的考友选择了D选项