试题查看

首页 > PMP考试 > 试题查看
【单选题】

You are working on a software development project. On this project, a number of tests must be performed, including some that must be performed multiple time. The project includes activities whose sequence is conditional based on the outcomes of prior activities. For example, if an error is discovered through inspection, the project’s design may have to be modified, creating the need for additional testing. The network technique best able to handle these situations is ______ .

A、PDM network
B.PERT chart
C.GERT network
D.ADM network
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

14%的考友选择了B选项

83%的考友选择了C选项

3%的考友选择了D选项

你可能感兴趣的试题

在组织内部,各职能部门间的工作整合通常由谁来负责()A.高级管理层B.项目业主或在新产品开发项目的初步规划期间,项目总费用估计为1000万美元,但也可能高达12你是一个项目经理,负责为组织采购项目管理培训服务。你选择卖方A来提供这项服务,卖项目团队中的一个小组刚刚完成了一项可交付成果,并提交给实施质量控制过程检查。你得YoufinallyhavebeenappointedprojectmanageCriticalchainisaschedulenetworkanalysist