【单选题】

A、control chart has all of the following characteristicsEXCEPT:

A、It illustrates how a process behaves over time.

B、It is used to determine whether or not a process is stable or has predictable performance.

C、It illustrates how various factors might be linked to potential problems or effects.

D、It can be used to monitor any type of output variable.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

6%的考友选择了B选项

83%的考友选择了C选项

9%的考友选择了D选项